- 15 -
Note
:
1. Export limitation refers to the system’s adjustment and controls based on the
power fed into the grid;
Power adjustment refers to limit the inverter maximum output power.
Export limitation function and power adjustment function can’t be open at the
same time.
After the export limitation function is set, the inverter needs to be restarted so
the function become effect.
2. When the Export limitation function is open, Power adjustment to the inverter
can’t be set.
3. Please restart the inverter if choose to open the 0-export function.
4. If the inverter is set with power adjustment function first and then users want to
start the export limitation function, he need to set the power limitation value
back to the maximum output power of the inverter to cancel the power limit.
E.g. The maximum power limit for Sununo Plus 1K is 110%.
Figure 3-14
Figure 3-15