Installation - S:FLEX Flat Direct
25
Mount the bracket 60 mm M10 onto the ground rail using a hammerhead bolt M8x25 and a self-locking nut. Ensure that
the hammerhead bolt is correctly aligned in the ground rail channel (torque 12-15 Nm).
11 mm
Alignment of hammerhead bolt
Force and form fit
Create force-fit and form-fit
connection
The ridge rail must always be
mounted below the bracket.
Use the adjustability due to
corrugation and elongated hole
It is important to ensure that the groove in the hammerhead bolt is perpendicular (at right angles to
the rail) after installing the clamp. Only then is the head of the hammerhead bolt correctly inserted
in the rail and the bracket is correctly attached.
Mount the ridge rail to the brackets using the M8x25 hammerhead bolt and the
locking nut. Make sure that the hammerhead bolts are correctly aligned in the
channel of the ridge rail (tightening torque 12–15 Nm) and that the ridge rail is not
under tension. To do this, use the adjustability that is created by the corrugation
of the components and the elongated hole. Ensure that a force-fit and form-fit
connection is created by interlocking the corrugations. The bracket must always
be attached to the upper side of the ridge rail.
Ridge
Eaves
Attachment to the ground rail:
Ground rail