Mounting The Flashings
The panels can now be piped up and the pipework inserted through the roof felt.
The panels should now be pressure tested to 6.5bar using either compressed air or glycol.
Note: If using glycol cover the panels for at least an hour before and at all times during the test.
The picture shown above assumes the panel doesn’t have an in built stat pocket. RM are gradually
introducing them across the range. If your panel doesn’t have a stat pocket please attach as photo
above. If there is a pocket in the panel please insert the probe into this and secure, the above fitting
is then replaced with a T-Piece complete with airvent.