1. Install electrical box and suggested remote
disconnect (supplied by others) in an area that can
be accessed for maintenance.
2. Bring signal wires from the machine controller to the
terminal blocks provided. The signal wires type will
need to match the type of valve provided (110VAC
or 24 VDC). Connect the limit switch wires to the
appropriate terminal blocks. Wire per instructions
provided,
Pages 10 & 11.
3. If the electrical box option is chosen, route the main
air line through the pressure regulator provided.
Maintain an operating pressure between 60 and 90
psi.
4. Connect an air line from the outlet of the pressure
regulator to the inlet (C) of the four way control
valve on the junction box or control box,
Figure 7.1
or 8.1.
5. Using the quick connections connect both air lines
from each end of the cylinder to outlet ports A and B
on the four way control valve,
Figure 7.1 or 8.1.
TERMINAL STRIP WIRING
1. Input signal for cylinder port A (24V or 110V).
2. Input signal for cylinder port B (24V or 110V).
3. 24VDC - P/N: 53300008
4. 110VAC - P/N: 53300007
JUNCTION BOX INSTALLATION (OPTIONAL)
Junction
and
Control
Box
1
Figure 7.1 - Junction Box 5220E003 Rev. C
6
5
4
3
2
A
C
B