Installation
17
20049577
GB
4.4
Operating position
4.5
Securing the burner to the boiler
4.5.1
Boring the boiler plate
Drill the combustion chamber locking plate as shown in (Fig. 11).
Tab. G
4.6
Blast tube length
The length of the blast tube must be selected according to the
indications provided by the manufacturer of the boiler, and in
any case it must be greater than the thickness of the boiler door
complete with its fettling.
For boilers with front flue passes 1)(Fig. 12) or flame inversion
chambers, protective fettling in refractory material 5) must be in-
serted between the boiler fettling 2) and the blast tube 4).
This protective fettling must not compromise the extraction of
the blast tube.
For boilers having a water-cooled front the refractory fettling 2)-
5)(Fig. 10) is not required unless it is expressly requested by the
boiler manufacturer.
WARNING
The burner is designed to operate only in
positions
1
,
2
,
3
and
4
(Fig. 10).
Installation
1
is preferable, as it is the only
one that allows the maintenance operations
as described in this manual.
Installations
2
,
3
and
4
permit operation but
make maintenance and inspection of the
combustion head more difficult.
DANGER
Any other position could compromise the cor-
rect operation of the appliance.
Installation
5
is prohibited for safety reasons.
2
3
4
5
1
D7739
Fig. 10
mm
A
B
C
RS 1200/E C01
19 11/16“
23 15/16“
51/64 W
Fig. 11
D455
5
2
1
1
3
3
8
7
20050807
Fig. 12