PUTTING INTO SERVICE

It is essential to perform the following checks before starting up 

or testing the functioning of the combination cylinder. In par-

ticular, check that:

 

− The supply cocks in the domestic water circuit are all open

 

− The water connections to the boiler and solar collectors 

have been made correctly

 

− All the pipes in the water circuit have been insulated in 

conformity to relevant standards

 

− The solar collector circuit has been correctly flushed out 

and  filled with water-glycol  mix,  and  all  air  has  been 

bled out of the circuit (see the manual for the solar col-

lectors)

 

− Start up the combination cylinder’s auxiliary heating 

boiler (if installed) as instructed in its own manual

 

− Put the solar collectors into service. See the manuals for 

the solar collectors and associated accessories.

 

9

The domestic hot water tank must be filled and pressur-

ised before the inertial storage cylinder is filled.

Solar heating circuit

Once the system has been started up, perform the following 

checks.

 

− Check that the flow rate in the solar collector circuit is 

equivalent to 30 l/h for each m

2

 of collector area

 

− Check that the solar collector circuit has been properly 

bled

 

− Check that the pressure of the system when cold is ap-

proximately 3 bar

 

− Check that the safety valve operates at 6 bar

 

− All the pipes in the water circuit have been insulated in 

conformity to relevant standards.

1

2

3

4

5

0

6

Heating circuit

Once the system has been started up, perform the following 

checks.

 

− Make sure that all pumps are free and rotate in the right 

direction

 

− Make sure that all circuits have been bled.

 

− Make sure that the boiler and solar collectors connect-

ed to the system shut down correctly when their mains 

power switches are turned OFF.

Provided the above checks have been completed satisfactorily, 

restart the system and verify its performance.

Technical Assistance Service

Summary of Contents for KOMBISOLAR 1000 3S

Page 1: ...cod 20145435 rev 2 07 2018 KOMBISOLAR 3S EN INSTALLATION OPERATION AND MAINTENANCE MANUAL...

Page 2: ...omfort in the home for many years to come Arrange for your R Combi nation cylinder to be serviced regularly by an authorised R service centre Their personnel are specially trained to keep your Combina...

Page 3: ...System layout 6 6 Technical specifications 8 7 Typical water system schematics 13 8 Location of sensors 15 9 Overall dimensions and water fittings 16 INSTALLER 10 Unpacking the product 18 11 Handling...

Page 4: ...t immediately Keep the product purchase documents to be presented to the R authorised Technical Assistance Service to request a service call under warranty 9 9Size the solar expansion tank so as to en...

Page 5: ...mwasserbetrieb Electrical consumption Stromaufnahme Maximum working pressure of inertial storage cylinder Max Druck Pufferspeicher Betrieb Maximum working temperature of inertial storage cylinder Max...

Page 6: ...torage cylinder temperature gauge 10 Domestic hot water outlet 11 DHW coil 12 Vent valve fitting 13 Outlet from boiler 14 Flow from second boiler 15 Heating system inlet 16 Return to second boiler 17...

Page 7: ...linder temperature gauge 10 Domestic hot water outlet 11 DHW coil 12 Vent valve fitting 13 Outlet from boiler 14 Flow from second boiler 15 Heating system inlet 16 Return to second boiler 17 Flow from...

Page 8: ...12 8 17 4 19 8 l DHW coil water capacity 23 6 23 6 30 4 30 4 l Top primary coil heat exchange surface 1 17 1 31 1 72 1 72 m2 Bottom primary coil heat exchange surface area 1 80 2 10 2 90 3 34 m2 DHW...

Page 9: ...of 3000 l h With T 35 C and primary temperature 80 C Performance achieved with boiler of suitable power configured for a flow rate of 1500 l h CONFIGURATION B KOMBISOLAR 3S Boiler Description KOMBISO...

Page 10: ...ary temperature 80 C Performance achieved with boiler of suitable power configured for a flow rate of 3000 l h CONFIGURATION D KOMBISOLAR 3S Boiler Description KOMBISOLAR 3S 430 550 750 1000 Domestic...

Page 11: ...E DROP mbar 600 700 800 900 500 400 300 200 100 0 0 1000 2000 3000 4000 5000 6000 430 550 750 1000 FLOW RATE l h Pressure drops KOMBISOLAR 3S BOTTOM COIL PRESSURE DROP mbar 600 700 800 900 500 400 300...

Page 12: ...12 GENERAL GENERAL Pressure drops KOMBISOLAR 3S DHW COIL PRESSURE DROP mbar 600 700 500 400 300 200 100 0 0 1000 2000 3000 4000 5000 550 750 1000 430 FLOW RATE l h...

Page 13: ...n troller 19 KOMBISOLAR 3S 430 550 20 Solar circuit expansion vessel 21 DHW user 22 Isolating valve 23 Thermostatic mixer valve 24 Safety valve 25 Bleed valve 26 DHW circuit expansion vessel 27 Filter...

Page 14: ...ISOLAR 3S 750 1000 20 Solar circuit expansion vessel 21 DHW user 22 Isolating valve 23 Thermostatic mixer valve 24 Safety valve 25 Bleed valve 26 DHW circuit expansion vessel 27 Filter 28 System cocks...

Page 15: ...nti freeze must be fitted with water dis connectors 8 LOCATION OF SENSORS R KOMBISOLAR 3S combination storage cylinders incorporate sockets for solar controller and boiler sensors Make sure that these...

Page 16: ...ler 1 1 4 F RA50 Return to boiler water 50 C 1 F CB Buffer tank charging 1 F RI SB Heating system return Inertial storage cylinder drain 1 1 4 F VS Vent valve fitting 1 F DESCRIPTION KOMBISOLAR 3S 430...

Page 17: ...Return to boiler water 50 C 1 F CB Buffer tank charging 1 F RI SB Heating system return Inertial storage cylinder drain 1 1 4 M VS Vent valve fitting 1 F DESCRIPTION KOMBISOLAR 3S 750 1000 A 365 365...

Page 18: ...he combination cylinder from the pallet To lift the combination cylinder remove the plug 2 and screw an eyebolt 1 of suitable capacity for the weight into the hole 3 1 2 3 1 1 If suitable equipment is...

Page 19: ...dren since it can become a potential hazard Dispose of packaging material in com pliance with applicable legislation 13 PLACE OF INSTALLATION R KOMBISOLAR 3S combination storage cylinders can be in st...

Page 20: ...The domestic hot water tank must be filled and pressur ised before the inertial storage cylinder is filled Solar heating circuit Once the system has been started up perform the following checks Check...

Page 21: ...reliability over time Have your combination storage cylin der serviced either by the manufacturer s Technical Assistance Service or by a qualified heating engineer at least once a year Perform the fol...

Page 22: ...emperature setting There is air in the primary circuit Bleed the circuit SOLAR COLLECTOR CIRCUIT FAULT CAUSE SOLUTION The buffer tank functions incorrectly or irregularly There is air in the circuit B...

Page 23: ...environment and save energy before leaving for the weekend or a short break etc provided outdoor temperatures will remain above ZERO simply adjust the combi nation storage cylinder s temperature cont...

Page 24: ...lo 7 37045 Legnago VR www riello com The manufacturer strives to continuously improve all products Appearance dimensions technical specifications standard equipment and accessories are therefore liabl...

Reviews: