Installation for Double Swing Gate

Step 1:

 

Disengage the clutch of the swing arms with the Manual Release Key. You can move the gate by 

hand, so the gate can swing freely during installation of the Electric Lock.

Step 2:

 

With the gates in the closed position, determine the best location for the lock and receiver . The 

lock and receiver must be level and aligned with the swing arms. The lock and receiver should 

have a solid surface or tube fence to provide stability.

Step 3:

 

For 

Metallic Tube Gates,

 if the thickness of the fence post is bigger than or equal to 3mm, you 

can thread on the fence post, and fasten the lock and receiver only using bolts (without nuts). 

Otherwise, drill holes throughout the fence post and fasten the lock and receiver with bolts, lock 

washers and nuts. Of course you could also weld them directly.

For a 

Chain Link Gates,

 you will need U Bolts, saddles, lock washers and nuts for the lock and 

receiver.

Step 4:

 

Recheck the locks position and alignment, make sure the electric lock is working correctly.

Step 5:

 

Connect the power cables for the lock to the control board of swing gate opener and Lock plus 

board. (See Figure E and F).

Note: Be sure that the clutch of the swing arms is engaged before you prepare to activate 

your opener (Use the Manual Release Key)

Summary of Contents for GTR169

Page 1: ...work correctly the gate must close firmly engaging the lock catch against the lock receiver 3 The Electric Lock must be installed on the outside of the gate if the gate is Push to Open 4 Due to the various mounting conditions mounting hardware is not provided Read this manual carefully to determine the mounting hardware required for your condition 5 For dual gate the lock must be installed on the ...

Page 2: ...of the fence post is bigger than or equal to 3mm you can thread on the fence post and fasten the lock and receiver only using bolts without nuts Otherwise drill holes throughout the fence post and fasten the lock and receiver with bolts lock washers and nuts Of course you could also weld them directly For a Chain Link gate you will need U Bolts saddles lock washers and nuts for the lock and receiv...

Page 3: ...he fence post is bigger than or equal to 3mm you can thread on the fence post and fasten the lock and receiver only using bolts without nuts Otherwise drill holes throughout the fence post and fasten the lock and receiver with bolts lock washers and nuts Of course you could also weld them directly For a Chain Link Gates you will need U Bolts saddles lock washers and nuts for the lock and receiver ...

Page 4: ...GTR169 Electric Lock Manual Rev 1 4 ...

Page 5: ...has been connected with the E Plus board Disconnect the terminals so that the electric lock wires can be fed through the access port and reconnected to the E Plus board The other wires of the electric lock should be connected to the control board using the following wiring diagram or the wiring diagram in the swing arm manual ...

Page 6: ...Rev 1 6 Connecting the Lock to the GTR058 and GTR100 Automatic Gate Kits The wires of the electric lock should be connected to the control board as the following wiring diagram and the wiring diagram in thein the swing arm manual ...

Reviews: