Startup

13. Check-Test

Start (cont'd)

KEY to Check/Test/
Startup Procedures:

Procedure applies to

all units.

¡

 Procedure only applies

to units with the
optional component
referred to in that
procedure.

o

1. Check to be sure that all field-installed accessories are installed.

o

2.  Check all field-installed wiring.

o

3.  Check all ductwork for obstructions; open all diffusers.

o

4.  Turn the three-position switch or optional summer/off/winter remote
console switch to OFF position. To prevent someone from turning the
system on, tape the switch leaving a note that it should be left in the OFF
position.

¡

5.  If the system includes an air control with a remote potentiometer, set
the position as follows::

Option AR19 (Variable Air Volume) - Turn full "open"
Option AR22 (Return Air) - Turn full "closed"

6. Check disconnect switch --

o

Turn disconnect switch OFF.

o

Check disconnect switch to be sure that it is tightly secured against the

cabinet.

o

If disconnect is fusible, check that fuses are installed. If fuses are not

installed, insert dual element time delay fuses sized 1.25 times the maxi-
mum total input amps. Verify continuity of fuses.

7.  Open the hinged gas/electric control compartment door --

o

Close all manual gas valves.

o

Check all wiring and wiring connections on gas controls and electrical

components.

o

If equipped with any manually reset devices such as an optional firestat

limit switch, a high limit switch, and/or optional high gas pressure switch,
reset devices. Check setpoint on the high ambient burner cutoff air control
(60°F).

8.  Open the hinged door to the blower compartment --

o

Remove any blocking and shipping supports.

o

Check that the blower belts are installed and have correct tension and that

pulleys are in alignment and locked to the shaft (See Paragraph 12).
Inside the compartment, remove the cover from the limit switch junction
box.

o

Reset manual limit switch.

o

Check wiring connections to limit switches, discharge air sensor, and

motor.

o

Replace the junction box cover.

9.  Turn ON gas supply valve and inlet manual shutoff valve on the mani-

fold.

o

Leak test gas connections upstream of the electric gas valve. Be sure all

connections are tight and leak tested. WARNING: DO NOT TEST WITH
OPEN FLAME.

o

Turn OFF manual gas valves.

10.  Turn blower service switch (Electrical Compartment, See FIGURE 26)

to OFF position. If present, verify that damper test switch is in TEST
position.

1.  Prepare system for startup testing --

o

Attach a slope gauge (0 to 1.0" scale) to the tubing connections in the

control compartment. The two connections are located just left of the
electrical box. Remove the caps on the 1/8" NPT test connections and
attach the slope gauge. (The recommended method for attaching the slope
gauge is to use field-supplied 1/8" female NPT x 1/4" OD barbed hose
connections.)

Before Startup

Summary of Contents for RDF 1-20-3

Page 1: ...tem provides tempered makeup air Makeup air is defined as air that enters a building or area due to negative pressure created by an air exhaust load in excess of the volume of entering air This system...

Page 2: ...account through standard engineering methods the structure s designed infiltration rate by providing properly sized relief openings by interlocking a powered exhaust system or by a combination of thes...

Page 3: ...e Sensor Option AR32 Toggle Switch Option AR36 Photohelic Pressure Sensor Option AR37 Photohelic Pressure Sensor If an optional remote console is ordered these controls are mounted on the console The...

Page 4: ...al to the width of the unit Top View Control Side Front View Rear View A Full Length of Outside of Curb Cap D Inside of Curb Cap Z Y B Cabinet Height 2 5 8 67 Control Compartment Blower Compartment Su...

Page 5: ...88 37 1 8 44 3 16 84 13 16 45 1 2 24 1 2 10 1 2 5 7 16 14 9 32 15 5 8 21 29 32 19 1 8 2 80 3 2 120 3 88 48 11 16 68 1 4 84 13 16 69 1 2 52 16 1 4 5 5 16 10 15 16 15 1 2 27 9 32 27 7 32 3 180 3 3 260...

Page 6: ...placed directly on a surface cross supports should be placed underneath the rails at the ends and at the cabinet joint Refer to FIGURE 4 IMPORTANT NOTE Mount an outdoor unit with a minimum of 14 clear...

Page 7: ...8 1 7 8 48 1 7 8 48 Roof Curb Ductwork for Bottom Discharge Option AQ1 or AQ3 Roof Curb Ductwork for Optional Return Air Airflow See IMPORTANT NOTE on the left Roof Curb Dimensions for Model RDF Serie...

Page 8: ...tolerance of 1 8 5 Level the roof curb To ensure a good weatherproof seal between the unit curb cap and the roof curb the roof curb must be leveled in both direc tions with no twist end to end Shim as...

Page 9: ...system is automatically controlled to maintain a set building pressure the en tering air will travel naturally toward the relief areas at the perimeter walls using the building structure as the distr...

Page 10: ...the type of construction of the roof wood joist steelbar joist steel truss pre cast concrete etc and the ceiling hung flush etc o Rectangular ducts should be constructed of not lighter than No 26 U S...

Page 11: ...er Light and Potentiometer If ordered the optional remote console is shipped separately Re mote consoles include terminal blocks for wiring Depending on what gas control or inlet air options were orde...

Page 12: ...normally open differential pressure switch that senses air pressure across the filter bank There are field installation procedures that must be done for the proper operation of the dirty filter indic...

Page 13: ...valve will not open If the actual temperature of the outside air is above the setpoint on the outside air control the burner will not ignite may modulate to satisfy discharge setting would shutdown co...

Page 14: ...t this switch The pressure null switch is Dwyer 1460 0 with a range of 01 12 w c The pressure null switch is a diaphragm operated differential pressure switch used in makeup air applications to contro...

Page 15: ...n AR33 or AR34 and or with Gas Control Option AG37 or AG51 If the system includes Air Control Option AR33 the discharge damper is con trolled by a field supplied 0 10VDC or 4 20 milliamp signal If the...

Page 16: ...dance with the requirements of the National Fuel Gas Code ANSI Z223 1 latest edition or CAN1 B149 1 and B149 2 Gas supply piping installation must conform with good practice and with all local codes R...

Page 17: ...te on a natural gas pilot supply pressure of 3 5 w c or propane gas of 6 0 w c Measure both operating pressure and pilot supply pressure with the blower in operation Manifold pressure is defined as th...

Page 18: ...ocedure in Paragraph 13 Motor Loads Use an ammeter to check motor amps Amps may be adjusted downward by reducing blower RPM or by increasing duct system static pres sure For accurate amps read the mot...

Page 19: ...k Test Start FIGURE 26 Control Locations in the Electrical Compartment RDF Series 3 Direct Fired Systems NOTE Locations may not be identical but controls should be smilar Check Test Startup Procedures...

Page 20: ...oIf equipped with any manually reset devices such as an optional firestat limit switch a high limit switch and or optional high gas pressure switch reset devices Check setpoint on the high ambient bu...

Page 21: ...oosen the setscrew on the side of the pulley away from the motor c Turn adjustable half of the pulley inward to increase blower speed One turn of the pulley will change speed 8 to 10 d Tighten the set...

Page 22: ...er 2 Model No AG3 Two Stage with Two Stage Ductstat MV 7 Serial No AG30 orAG31 Maxitrol Series 14 Outside Air Only Amplifier A1014 MV 8 Serial No AG32 Maxitrol Series 14A Outside Air Only Amplifier A1...

Page 23: ...k the main burner inlet gas pressure If the main inlet gas pressure is lower than stated on the rating plate full burner firing rate will not be achieved Check main gas supply service regulator for ad...

Page 24: ...irements in the installation codes and operating instructions The amount of air over the burner must be within the specified range The burner profile plates are set at the factory to match CFM require...

Page 25: ...ate N A 2 91584 2 98764 Filter Block Off Sections N A 6 95335 6 96335 Permanent Filters 12 N A 1 87251 2 94383 Sheetmetal Screws 10 x 1 2 long Screws 1 4 20 x 5 8 long bolt type Hex Nuts 1 4 20 Keps S...

Page 26: ...inet Post Bottom Filter Channel with Blockoff Plate assembled in 1B P N 91578 Intermediate Cabinet Post Center Channel Assy Step 1C Assemble Outer Side of Filter Rack Options AS6 and AS7 only Parts Re...

Page 27: ...tach Assembled Cabinet Section 4 Assemble Air Inlet Hood Section P N 91569 Right Side of Hood P N 91568 Left Side of Hood Step 4A Attach Hood Sides Attach the sides to the interme diate posts and bott...

Page 28: ...er Louver Supports Step 4E Install Louvers Parts Required Two factory assembled louver sec tions 19 screws 1 2 long and five Tinnerman clips Position one louver section in the left side of the hood at...

Reviews: