1.
Secure the front of the trusses to the H1 hangers with 1-1/2" hanger nails.
2.
Locate (4) four 21"x48-3/4" soffit panels under the front overhang. Cut the first soffit panel
along 'LAP' edge so the tongue edge is centered on the second truss. Use 6d galv. nails.
3.
Install another soffit panel. Cut the last panel to fit.
Step 15 Install Gable Trim
Step 14 Install Front Soffit
Install the 1x4 gable trim extending 1/2" above the 2z4
on the gable. When installed later, the roof sheathing
will be flush with the top of the trim.
Siding/Soffit Panel
Trim 1/2"
Above 2x4