Commissioning
16 / 44
TARAtec 9/10
4
Commissioning
4.1
Installation requirements
The following installation requirements must be satisfied:
Continuous power supply and presence of water being measured
Flow rate as specified on the data sheet
Constant through flow rate
There must be disinfectants present in the water being measured.
Galvanic separation of the electrical connection (if not present in the
sensor, see data sheet, section 1.2, p. 5)
Make sure that the measuring water does not evolve gas at the
measurement point.
4.2
Preparation of the sensors
Pull the protective cap [3] off the membrane cap [2].
Unscrew the membrane cap [2] from the sensor body [1].
Fig. 3:
Unscrewing the membrane cap
1
Sensor body
2
Membrane cap
3