4. CONSTRUCTION READINESS, INSTALLATION
The installation may only be carried out by a person possessing a valid manufacturer‘s
authorization.
4.1. Scope of supply
- RTC 13e Heat Pump
- Installation and Operation Manual
- 2 compensators to protect the plate heat exchanger in the heat pump against frost
rupture
4.2. Installation preparation, transport
The installation must be carried out
by a qualified person in accordance
with the applicable standards and all
regulations concerning occupational
safety must be observed.
- The heat pump shall be
transported and stored in an
upright position only.
- Check that the product has
not been damaged in transit.
Report immediately any
transport damage to the carrier
and supplier.
- Transport the unit to the
installation site before removing
the packaging.
- Move the product with a pallet
truck or forklift if possible.
- It is possible to use lifting straps
tied around the pallet, however
only if the packaging (the
wooden frame) had not been
removed.
-
MIND THE DIFFERENT WEIGHT
OF THE RIGHT AND LEFT SIDE
OF THE HEAT PUMP!