8
G51 Zero Clearance Kit
INSTALLATION
1)
Assemble Zero Clearance box as per instructions on
page 6. DOT NOT INSTALL FRONT PLATE.
2)
Place the unit on the stand-offs in the Zero Clearance
box.
3)
Slide the unit in all the way back.
4)
Run required gas and electrical connections to the
Zero Clearance box, both are located on the left hand
side of the unit. See "Gas Supply Line" on page 9 and
"Electrical Supply" on page 9.
5)
Attach flue collar to the top assembly. Align with holes
in ZC box and secure with 4 screws.
6)
Install front panel of zero clearance box, secure using
6 screws.
7)
Make the final gas and electrical connections as per
the Instruction manual.
Zero Clearance Box with
unit in place.
Zero Clearance Box assembled.
ZERO CLEARANCE
BOX INSTALLATION
Summary of Contents for 390-900