page 14 of 19
Plumbers, please ensure a copy of the installation
instructions is left with the end user for future reference
Domaine Semi-Recessed Wall Hung
VANITY INSTALLATION
1. LOCATION
3. LEVELING
4. SECURING THE CABINET
5a. FIX TOP / BASIN
6. SEALING
2. PREPARING THE CABINET
After completing the Prior to Installation Checklist, mark the position of
the top of the vanity. Don’t forget to factor in the top/basin thickness to
get the correct height.
Note: Vanity must attach to a minimum of two support beams, mark
these positions.
Remove doors and drawers. Measure correct plumbing loctions and
drill holes for plumbing in the back panel and/or base of the cabinet with
an appropriate sized hole saw. Pre-drill screw locations for fastening to
wall.
Position the vanity over the pipes in the correct position and fix with a
single screw in centre of vanity to hold in place.
Check the vanity is completely level.
Wall Hung vanities: You may want use a level support/noggin to assist
while leveling.
Floor Mount Vanities: You may need to pack the vanity to ensure it is
sitting level & square on the floor.
Using a non-acidic silicone, apply a continuous bead of silicone to the
top four edges of the vanity and at the back where the top meets the
wall. Position the top so it has equal overhang on each side, ensuring
the top surface is level.
If using a seperate basin, position in place and fully seal the basin to the
top /cabinet using a continuous bead of silicone.
Note: Seal any visible gaps between the cabinet and the top and basin
with continuous bead of silicone.
Apply non-acidic silicone to all edges where vanity top and cabinet
meet the wall and floor.
Materials used in the construction of this unit are water resistant NOT
water proof, so all areas need to be sealed to prevent water penetration.
Note: Gap sealant can be used in place of silicone where the unit meets
tiled surfaces.
Securely fasten the vanity to the wall through back of vanity with
appropriate screws/bolts at TOP and BOTTOM of cabinet. Fix the
cabinet through the top left and right hand brackets and evenly space
apart the horizontal fixings at a maximum of 300mm apart. For the
bottom start the fixing points no further than 100mm from each end of
the cabinet and no higher than 50mm from the base panel.
Note: Where a stud or support beam cannot be located, use an
appropriately sized hollow wall anchor. Vanity must attach to a minimum of
two support beams. Ensure fixings clear all water/electrical services in wall.
Front
Back
Diagonal
Sides
LEVEL
All edges
where water
penetration
can occur
SEAL
Equal overhang
300mm
300mm
300mm
page 3 of 8