24
681
MIN.
300
741
700
MIN.
400
1320
MIN.
600*
500*
MIN.
300
24
5 - POSITIONING
REQUIREMENTS FOR INSTALLATION OF THE PLANT - POSITIONING
The most important thing to do before installation of the boiler is to set aside a suitable area that meets the minimum requirements for
installation.
•
the minimum clearance in front of the product
for the purpose of cleaning, maintenance, etc. must be
700 mm
;
•
the minimum permissible distance between the back of the product and a wall must be
400 mm
;
•
the minimum distance between the top of the product and a wall (ceiling) must be
600 mm
to ensure easy access to the heat
exchanger for cleaning and maintenance (e.g. for removing ash and possible installation of the pellet suction kit);
•
the minimum clearance between the product and the wall (side) must be
300 mm
.
SELECTA BOILER MINIMUM REQUIREMENTS
* in the event of suction kit installation