[8] Commissioning
Important!
Ensure proper mechanical an electrical installation before commissioning the solar inverter.
Check the cables to ensure, that they are in sound condition.
The DC-connectors must not be disconnected under load. Always switch off battery first !
To ensure proper function of the AC system, a RCT Power Sensor is required, which transmits the
grid feed-in power to the inverter.
If a storage system already exists, this information can also be transmitted via LAN / WLAN and
thus dispenses with the RCT Power Sensor.
In order to make visible an external power generator on the App, it must be connected to a digital
input. This may require a further energy meter with pulse output.
Further configuration inter alia for the networking of RCT Power devices LAN / WLAN can be found
in the manual on ou website
[8.1] Switch on Inverter
Step
Description
1
Establish grid connection via the external circuit breaker.
2
If there’s a 3-phase mains, the display of the device
switches on.