2–17
Installation
F232048
Elevated Base Frame Installation
Factory-built elevated steel base frames are
designed to meet the specifications of the
appropriate model dye/extractor. See Figure 2-
16.
Figure 2–16.
Use Figures 2–11 through 2–15 and the
following instructions as a guide to step-by-
step installation of the elevated base frame.
1.
Use the elevated base frame as a template
by positioning the frame in the desired
location and marking the pre-drilled
mounting holes on the floor. See Figure 2–
17.
Figure 2–17.
2.
Adjust the drill depth gauge to match the
length of the J-bolt, minus
1-1/2" (38 mm). See Figure 2–18.
Figure 2–18.
3.
Drill and chisel out a conical hole large
enough to accept the J-bolt.
See Figure 2–19.
Figure 2–19.