SEE FIG. 20 & 21
After 15 minutes of the boiler burner running:
1.
Remove top LH door (Rayburn 680KCD C/F only),
store in a safe place.
2.
Open control door.
3.
Remove the plugging screw and insert the sensing
end of a portable indicator to check the CO
2
(Carbon
Dioxide) level. Adjust the boiler burner air intake until a
reading of 11.0/11.5% is recorded on the indicator.
SEE FIG. 21
Remove the CO
2
sampling tube and using the same hole
for flue sampling, insert the sensing end of a Baccarach
Smoke Pump and check that the smoke in the boiler
flueways does not exceed No. 2 on the scale.
Replace the plugging screw and plug.
Switch off the boiler burner.
COOKER BURNER - SEE FIG. 21
Switch on cooker burner.
After 15 minutes of the cooker burner running.
Repeat the above procedures for the cooker burner. To
sample the flue gases from the cooker burner lift up the
RH insulating cover and remove the countersunk headed
screw in the hotplate. The cooker burner should be set to
11.0/11.5% maximum Smoke No. 2.
Replace the countersunk headed screw on completion
ensuring that it will not interfere with any pots and pans
placed on the hotplate.
16
SET COMBUSTION AIR
CHECK SMOKE
Re-commissioning
Fig. 20
DESN 515955
+
-
Fig. 21 - Rayburn 680KCD C/F
DESN 516264
Summary of Contents for 680KCD C
Page 9: ...Cleaning 9 Fig 6 ALL BAFFLES MUST BE STACKED IN PLACE AS DIAGRAM ABOVE ...
Page 22: ...22 Fig 31 DESN 514774 Replacement of parts Electrical controls ...
Page 23: ...23 Fault Finding Fig 32 Rayburn 600 700 Wiring Diagram 111MB for Individual Satronic boxes ...
Page 29: ...Fault Finding 29 Fig 34A DESN 516838 ...
Page 30: ...30 Fault Finding ...
Page 31: ...31 Fault Finding ...
Page 33: ...33 ...
Page 34: ...34 ...
Page 35: ...35 ...