Wiring Call Boxes to Supervisor Board
1.

 Using the provided RJ11 pigtail cables, plug the RJ11 end of the cable into the RJ11 jack on the front of the 

    Supervisor Board. The wire color on the jack should match what is punched down on the back. 

2.

 Splice field station wiring on to pigtail sides of the RJ11 harness.

    

Note:

 The maximum wire run length is 4,000 ft. 

Wiring Outside Phone Lines to Supervisor Board

Ports 19 and 20 on the Supervisor Board are flex ports. They can be used for emergency 

phones or outside phone lines. 

1.

 Take one of the RJ45 wiring harnesses and connect the RJ45 side to the TWT port 

    on the Distribution Module (refer to card break down to identify).

2.

 Follow one of the options below:

    

Note:

 If using multiple Supervisor Boards, it is recommended to use port 19 and/or 

    20 on the last board so the phone extensions are not out of order.

    

a.

 If using one phone line, use the 110 style punch down tool to punch down the blue, 

    blue-white pair of wires on to the number 20 punch down block on the back of the    

    Supervisor Board.

    

b.

 If using two phone lines, use the 110 style punch down tool to punch down the blue, 

    blue-white pair on to the number 20 punch down block. Then, take the orange, orange-

    white pair and punch it down on to the number 19 punch down block on the back of 

    the Supervisor Board.

3.

 Connect the phone line to the RJ11 jack on the front of the Supervisor Board that 

    matches the same number wires that are punched down on the back of the board 

    (Ex: Punch down block 20 = RJ11 port 20).

4.

 Change the dip switch on the top edge of the board to “LINE IN” and “ENABLE” on any 

    port with a phone line connected to it. 

Connecting the Power Supply

Do not apply power to the Supervisor Board until all punch down connections are made.

1. 

Attach the su12vdc Power Supply to the appropriate terminals on the Supervisor Board.

   •  Insert the +Wire into the +Connector

   •  Insert the -Wire into the RETURN Connector

   •  Secure the wires by screwing down the capture clip

Note: 

For systems larger than 16 zones, connect the subsequent Supervisor Boards in series by connecting 

any additional wire to the +Connector and to the RETURN Connector for feeding power to the next board in the 

system. Wire up to 2 Supervisor Boards per transformer.

POWER IN

RETURN

+ 12VDC

12 VDC

POWER 

SUPPLY

SUPERVISOR BOARD 1

POWER IN

RETURN

+ 12VDC

SUPERVISOR BOARD 2

Summary of Contents for 2500 SPRVSR Series

Page 1: ...pervisor Board 2500 __SPRVSR Installation Operations Manual N56W24720 N Corporate Circle Sussex WI 53089 800 451 1460 www rathcommunications com RP8500SPRVSR Ver 8 07 20 Made in the USA 3 Year Warrant...

Page 2: ...y assist with site preparation installation and maintenance It is our sincere hope that your experience with us has and will continue to surpass your expectations Thank you for your business The RATH...

Page 3: ...ex Ports Can be Used for Outside Phone Lines or Call Stations For 12 16 zone systems one Supervisor Board is included Wire as shown below For 28 36 zone systems two Supervisor Boards are included Wire...

Page 4: ...4 Phones 4 Phones 4 Phones 4 Phones 4 Phones 4 Phones Flex Ports Can be Used for Outside Phone Lines or Call Stations The second through fifth cards will always be used for connecting additional Emerg...

Page 5: ...Phones 4 Phones 4 Phones 4 Phones 4 Phones Flex Ports Can be Used for Outside Phone Lines or Call Stations Note Do not follow the color scheme on the punch down blocks themselves 56 92 Zone Distributi...

Page 6: ...te The numbering pattern continues on all subsequent cards Depending on the number of zones needed some cards will be left empty and will have no connections S01 S04 S05 S08 S09 S12 2019 2020 2033 203...

Page 7: ...use the 110 style punch down tool to punch down the blue blue white pair on to the number 20 punch down block Then take the orange orange white pair and punch it down on to the number 19 punch down bl...

Page 8: ...bracket or to a 19 rack not included Complete System Connections 1 Plug the power transformer into the power source wall outlet or UPS 2 Ensure the LEDs associated with the connected Supervisor ports...

Page 9: ...bove the port will clear 5 After all errored devices are reconnected the green system status light should illuminate within 3 minutes Typical System Layout Distribution Module 2500 UPS Monitor Fire Co...

Reviews: