• After successfully numbering a unit, change the number displayed on the
CONNECT unit and repeat the process above for all required units. Note that
the Polling feature of WES
3
can perform an automatic integrity test of the first 128
WES
3
units added to a network. Additional units can be added to the network,
but will be excluded in the integrity test.
• If the red LED illuminates, pairing has failed. Ensure the unit to be numbered is
turned on, and repeat the Unit Numbering process, ensuring you haven’t used the
same number twice.
4. Add Units to an Existing Site Group
Repeat steps 2 and 3.
5. Position Units
• Once activated and paired, WES
3
units can be installed on site. Ensure any
applicable local guidelines or standards regarding locating units on site are
adhered to.
• Wherever possible, avoid positioning the unit directly adjacent to metal frames,
electric cables and similar equipment that may interfere with the signal strength.
6. Securely Fix the Units in Place
• Each WES
3
unit must be securely fixed in place and the tamper switch on the
rear of the unit must be in contact with the wall or ceiling.