a.
Connect the
even
pinspotter’s cycle control (
10
th
frame) wires to terminals #
1
& #
2
.
b.
Connect the mechanic call control wires to terminals #
3
& #
4
.
c.
Connect the
odd
pinspotter’s cycle control (
10
th
frame) wires to terminals #
5
& #
6
.
15.
Secure all of the wires connected to junction blocks J1 and J2 to the inside of the
control box using the cable clamps provided.
16.
Verify that the voltage selector switch on the control board in the Ball Lift control
box is selected to the correct voltage – down for 230 volts and up for 115 volts –
and install the control box cover.
17.
Remove the five screws from the underside of the blower cover, remove the cover,
and verify that the blower is wired for the voltage of the circuit connected to the ball
lift. There are two 5-pin connectors on the wire harness leading to the blower. One
connector is wired for 115-volt power and the other for 230-volt power. Check the
tag by each connector and, if necessary, change the connector that is plugged into
the blower to match the voltage of the power supply.
18.
Reinstall the blower cover.
!