Receiving
The shipment should be thoroughly inspected as
soon as it is received. The signed bill of lading is
acknowledgement by the carrier of receipt in good
condition of shipment covered by our invoice.
If any of the goods called for on this bill of lading
are shorted or damaged, do not accept them until
the carrier makes a notation on the freight bill of
the shorted or damaged goods. Do this for your
own protection.
NOTIFY
Quality Lifts
AT ONCE if any hidden loss
or damage is discovered after receipt.
IT IS DIFFICULT TO COLLECT FOR LOSS OR
DAMAGE AFTER YOU HAVE GIVEN THE
CARRIER A CLEAR RECEIPT.
File your claim with
Quality Lifts
promptly.
Support your claim with copies of the bill of lading,
freight bill, and photographs, if available.
Fig 3 –
Package Components
Component Packing List
ITEM
#
QTY/
LIFT
DESCRIPTION
1
1
IDLER RUNWAY ASS’Y
2 1
POWER
RUNWAY
ASS’Y
3 1
POWER
COLUMN
ASS’Y
4
3
IDLER COLUMN ASS’Y
5 2
ENTRANCE
RAMP
6
2
CROSS BEAM ASS’Y
7 1
POWER
UNIT
8
2
FRONT WHEEL STOP
9
2
REAR WHEEL STOP
10
1
MECHANICAL LOCK BAR
11 8
SHIPPING
HARDWARE
12
2
SHIPPING BRACKET WELD
I
NSTALLATION
I
MPORTANT
:
Always wear safety glasses while installing lift.
T
OOLS
(
MINIMUM REQUIRED
)
a. Tape measure, 25ft
b. Chalk
line
c. 4ft
level
d. 10” & 12” adjustable wrench
e. Standard open end wrenches 3/8”, 7/16”, 1/2",
9/16”, 5/8”, (2) 11/16”, 3/4", 15/16”, 17mm
f. 6mm
allen
wrench
g. Box
knife
h. Thread locking compound
i. Needle
nose
pliers
j.
Hammer drill with 3/4” diameter carbide tipped
bits
(Optional)
k. 2lb
hammer
l.
Torque wrench: 150 foot pounds minimum with
1 1/8” socket
(Optional)
m. 8 ft. Step ladder
n. Blocking – (4) 4x4x30”, (4) 1x4x12”
o. Transit for leveling alignment lift.
p. Power Unit requires three gallons of clean
10wt anti-foam anti-rust hydraulic oil or Dexron
III ATF.
D
O
N
OT
U
SE
O
ILS
W
ITH
D
ETERGENTS
L
AYOUT
1) Lay out the service bay according to the
architect’s plans or owners instructions
(see
Fig 1
). Be certain that the proper conditions
exist, see pages 2 & 3.
2) Unpack lift. Remove all packaging from Power
Runway (power runway has four cable
sheaves at rear end) and pull threaded cable
ends out. Make sure the cables are in the
proper sheaves at the 4-stack,
Fig 6
.
3) Remove the mechanical lock release bar from
the Idler Runway.