Model Q4P09
Installation, Operation and Maintenance
11
Rev 8/18/09
Q4P09-IOM-Q.doc
O
PTIONAL
A
CCESSORIES
O
IL
D
RIP
T
RAY
(Q4P09DT)
1) Place drip tray between runways in the Jack
rail,
Fig 19
.
2) Slide along jack rail until its in desired
location.
Fig 19 – Oil Drip Tray
S
TORAGE
P
LATFORM
(Q4P09SP)
1) Up to four Storage Platforms can be placed
between the runways,
Fig 20
.
Fig 20 – Storage Platform
J
ACK
P
LATFORM
(Q4P09JT)
1) The Jack Platform rest on the jack rails
between the runways. It can be positioned
as needed along the rail,
Fig 21
.
Fig 21 – Jack Platform
M
OBILITY
K
IT
(Q4P09CS)
1) This set of four casters when attached to the
cross beams of an unloaded lift,
Fig 22
, pick
the lift up and allow it to be rolled to a
different location.
Fig 22– Mobility Kit
H
AND
O
PERATED
R
OLLING
J
ACK
(QRJ04H)
1) Move the jack into under vehicle and extend
the arms to the pick up points.
2) Make sure the lowering valve is closed all the
way by turning the knob clockwise,
Fig 23
.
3) Raise vehicle desired height, rest the jack in
one of the jack locks.
4) To lower, pump the jack to raise it enough to
disengage the lock, and turn the lowering
knob counter-clockwise.
Fig 23 – Rolling Jack
E
XTENDED
A
LUMINUM
R
AMPS
(Q4P09ER)
1) Install in the rear of the runway by placing the
two studs in the slotted holes.
2) Remove before raising the lift.