P
OWER
G
EN
R
EPORTS
AND
C
HECKLISTS
4
9
• Verify Customer electrical load matches Site Survey before
connecting customer electrical load to PowerGen
• Customer load to be connected only after initial running of the
PowerGen
• Check wiring, check grounding
10
Reconnect customer electrical load to Qnergy terminal blocks after
verifying customer loads:
• Measure voltage and current output from PowerGen
• Verify load does not exceed generated power
11
Side panels installed and front access door closed
12
Verify no active warnings
13
Mention and non-standard activity to engineering change done on the
PowerGen that was not mentioned above or not according to the formal
Installation Manual from Qnergy:
Customer Signature
Date (DD/MM/YYYY)
Commissioning Agent Signature
Date (DD/MM/YYYY)
Table 1-4 Commissioning Checklist
Step #
Step
Initials