INSTALLATION AND OPERATION MANUAL SOLAR MODULES Q.PEAK DUO M-G11.X

INSTALLATION AND OPERATION MANUAL SOLAR MODULES Q.PEAK DUO M-G11.X

14

15

3 Installation

3.3 Module installation

Option 1:

  Fasten the module with 4 clamps in the specified 

clamping range, see Fig. 2, p. 7.

  Tighten clamps according to manufacturer’s 

instructions.

  Maintain an interval of at least 10 mm between two 

modules along the short side and 5 mm along the 

long side.

10 mm

5 mm

EU

Note! Module damage may occur!

  Do not subject modules to mechanical tension. Max. 

torsion 10 mm / m.

Option 2:

  Install the module at the 4 mounting points,  

see Fig. 2, p. 7.

  Tighten screws according to manufacturer’s 

instructions.

Option 3:

  Install the module using mounting profiles,  

see Fig. 2, p. 7.

4 Electrical connection

4.1 Safety

Danger! 
Risk of fatal injury due to electric shock!

When disconnecting an electric circuit carrying direct current, 

electric arcs can occur that may result in life-threatening injuries.

  Do NOT unplug the cable when under load.

  Do NOT connect any exposed cable ends.

  Electrical work may only be performed by qualified and skilled 

personnel (see page 3).

A solar module generates electrical current and voltage even 

at a low intensity of illumination. Sparks and electric arcs may 

result from the separation of a closed circuit. These can result 

in life-threatening injuries. The danger increases when several 

modules are connected in series.

  Please be aware of that the entire open circuit voltage is active 

even at low levels of solar irradiation.

  Please follow the valid national regulations and safety 

guidelines for the installation of electrical devices and systems.

  Please make sure to take all necessary safety precautions. With 

module or phase voltages of more than 120 V, the safety extra-

low voltage range is exceeded.

  Carry out work on the inverter and the wiring with extreme 

caution.

  Ensure that the modules are disconnected at the inverter prior 

to separation.

  Be sure to observe the time intervals specified by the inverter 

manufacturer after switching off the inverter.

  Make sure that the plugs can not be connected unintentionally.

  Before working on the contacts, check them for safety extra-

low voltage.

Danger! Risk of fatal injury due to electric shock!

  Only use dry, insulated tools for electrical work.

Danger! Risk of fatal injury due to electric shock!

  Never open the junction box.

  Do not remove bypass diodes.

Danger! Risk of fatal injury due to electric shock!

  Never touch live contacts with bare hands.

  Cover connectors by suitable protective caps until 

installation.

Danger! Risk of fatal injury due to electric shock!

  Insulate any exposed cable ends.

  Only connect cables with plugs.

Summary of Contents for Q.PEAK DUO BLK M-G11

Page 1: ...Installation and operation manual Q PEAK DUO M G11 X solar module series...

Page 2: ...the solar modules This manual Other applicable stipulations such as country specific regulations for pressure equipment operational safety hazardous goods and environmental protection Regulations and...

Page 3: ...WARRANTY AND MAY CREATE A SAFETY HAZARD AND RISK PROPERTY DAMAGE THIS INCLUDES IMPROPER INSTALLATION OR CONFIGURATION IMPROPER MAINTENANCE UNINTENDED USE AND UNAUTHORIZED MODIFICATION 2 Planning 2 1 T...

Page 4: ...the ground the roof or the fa ade Forces acting on the module are relayed to the mounting substructure Ensures sufficient rear ventilation of the module Avoid the usage of different metals to prevent...

Page 5: ...values have been determined with the following clamp parameters clamp width 40mm and clamp depth 10mm The system installer is responsible for the determination of location specific load requirements...

Page 6: ...mum number of modules in the string Parallel Connection Modules may be damaged by the occurrence of reverse currents caused by module defects ground leaks or defective insulation Ensure that the maxim...

Page 7: ...tion cables or junction box Carry modules upright and horizontally as shown Note Module damage may occur Never step on modules Do not subject modules to any mechanical stress Do not allow any objects...

Page 8: ...ctric arcs may result from the separation of a closed circuit These can result in life threatening injuries The danger increases when several modules are connected in series Please be aware of that th...

Page 9: ...nly be performed by qualified and skilled personnel see page 3 Ensure correct polarity Use solar cables for the connection at the junction box outlet Only interconnect connectors of the same type and...

Page 10: ...7 Disposal Do not disconnect modules by yourself Please contact an installer or Qcells Technical Customer Service Department Dispose of modules in accordance with the local disposal regulations Ensure...

Page 11: ...ay occur Remove snow and ice carefully without force e g with a very soft broom Do not scratch off dirt Module cleaning has to be done by qualified personnel according to the state of the art and taki...

Page 12: ...manual solar modules Q PEAK_DUO_M G11 X_modules_series_30T_2022 07_Rev04_EN Hanwha Q CELLS GmbH OT Thalheim Sonnenallee 17 21 06766 Bitterfeld Wolfen Germany EMAIL WEB TEL FAX sales qcells com www qc...

Reviews: