PV500-24 03-99
Section 24
1
INSTALLATION & MAINTENANCE MANUAL FOR
QuickDraw
INSTANTANEOUS
ENERGY: WATER TO WATER
U-TUBE SINGLE-WALL & DOUBLE-WALL HEAT EXCHANGERS
TYPICAL CONSTRUCTION
FIGURE 24-1
1. U-tube Heat Exchanger
9. Boiler Water Temperature Gauge *
2. Boiler Water Inlet
10. Tridicator *
3. Boiler Water Pump
11. Flow Switch *
4. Control Enclosure
12. Relief Valve (AGA optional)
5. Intratank Circulator
13. Tank Purge Valve *
6. Potable Water Inlet
14. Boiler Water Outlet
7. Potable Water Outlet
15. Check Valve
8. Tank Drain
* Optional
CAUTION: TEMPERATURES HIGHER THAN 125
°
F. INCREASE THE RISK OF SCALD INJURY!
IMPORTANT: Clearances for servicing and inspection are 18” at top, sides and rear and a
minimum of one tank diameter in front.