5) Adjust the position of rubber seal on the hanger bolt (ER-HB-8/150) 
to ensure hanger bolt have minimum 25 mm penetration depth into the 
wood purlin.
Drive the hanger bolt on the wood purlin till the rubber seal is firmly 
flush on the tile and turn the nut down till touching the rubber seal. 
Please turn another 4 threads cycle to press the rubber seal.

Note: 
1) Purlin thickness and tile thickness need to be verified to decide 
position of rubber seal for appropriate penetration depth; 
2) It is recommended to apply Sikaflex on the area around 10 mm hole 
of the tile before fixing hanger bolt. Please refer Sikaflex instructions for 
use.

Figure 4.2.5

Figure 4.2.6A

Figure 4.2.6B

6) Screw out the top nut of hanger bolt, connect and adjust tin foot position and tighten the top nut with the 
recommended torque of 16~20 N•m.

7)  Rail, clamps, and panel installation

Please refer to 

PV-ezRack® Solar Roof Installation Guide

 for steps on installing rails, clamps and PV panels. 

The guide also gives our standard engineering spacing of hangar bolts based on site conditions.

Note: Hangar bolt spacings are equivalent to tin feet spacings in the installation guide.

Summary of Contents for SolarRoof Slate Tile

Page 1: ...SolarRoof Slate Tile Code Compliant Planning and Installation Guide V1 0 Complying with AS NZS1170 2 2011 AMDT 2 2016 Ver 1 0 Last Updated Oct 2021 ...

Page 2: ...Verifying atmospheric corrosivity zone of installation site by referring to AS 4312 2008 or consulting local construction business to determine appropriate products and installations Complying with all applicable local or national building codes including any updates that may supersede this manual Ensuring that PV ezRack and other products are appropriate for the particular installation and the in...

Page 3: ...g Marker Pen Slate Rip Lead Flashing Tools and Components Tools Manufacturer Clenergy Components ER EC ST End Clamp ER IC ST Inter Clamp C U 30 46 G Universal Clamp with Grounding Clip C U 30 46 Universal Clamp ER EC DU35 40 End Clamp Dual 35 or 40mm ER EC DU40 46 End Clamp Dual 40 or 46mm ER R ECO ECO Rail ER SP ECO Splice for ECO Rail ER I 02 Flat Tile Interface SCO ECO 380 Side Channel Cover fo...

Page 4: ...ant Planning and Installation Guide V1 0 Complying with AS NZS1170 2 2011 AMDT 2 2016 Manufacturer Clenergy Components EZ RE 200 Roof Hook Extender ER HB 8 150 Hanger Bolt for wood purlin ER HB MP 8 150EP Hanger Bolt for metal purlin Tools and Components ...

Page 5: ...NZS1170 2 2011 AMDT 2 2016 System Overview A End Clamp B Inter Clamp C ECO Rail D Tile interface A End Clamp B Inter Clamp C ECO Rail D Tin interface E Hangar Bolt A A A A D D D D E E B B B B C C C C PV ezRack SolarRoof Slate Tile with Tile Interface PV ezRack SolarRoof Slate Tile with Hanger Bolt System Overview ...

Page 6: ...the roof battens 2 Removing Slate Tiles Determine the positions of the tile brackets according to your plans Take out the nails on the slate tiles and remove two or three slate tiles at the marked positions Slate tiles are removed by using a slate rip which unhooks the nail that secures the slate By hitting the slate rip handle with a hammer the nail is pulled out Thus allowing slate to be removed...

Page 7: ...screwdriver until the screw is fastened Use wooden packers to lift the tile bracket so that the base does not rest on the tile as shown in Figure 4 1 4B 5 Apply flashing around Tile Bracket For prevention of water leakage it is important to using flashing to secure the installation against rainwater Cut out lead flashing to fit the profile of the tile bracket Cover the bracket with the flashing an...

Page 8: ...also gives our standard engineering spacing for tile interface based on site conditions 2 Hangar Bolt Installation 1 Purlins are to be identified when opening tiles and their positions are marked out on the tiles 2 Based on installation plan and Hanger bolt spacing information hanger bolt locations are marked on the tiles Note Hangar bolt spacing is equivalent to the tin spacing which is provided ...

Page 9: ...ickness need to be verified to decide position of rubber seal for appropriate penetration depth 2 It is recommended to apply Sikaflex on the area around 10 mm hole of the tile before fixing hanger bolt Please refer Sikaflex instructions for use Figure 4 2 5 Figure 4 2 6A Figure 4 2 6B 6 Screw out the top nut of hanger bolt connect and adjust tin foot position and tighten the top nut with the recom...

Page 10: ...1170 2 2011 AMDT 2 2016 Certification Letter The accredited spacings depend on the method of installation Please refer to table below for reference to the correct manual for your installation method Mounting System Setup Manual Tile Interface PV ezRack Solar Roof Installation Guide Hangar bolts Certification Letter ...

Page 11: ...stomized Product Product Warranty Corrosivity Category 1 2 and 3 Corrosivity Category 4 Corrosivity Category 5 1 Aluminium Components 6005CL T5 mill finish Standard 10 years 10 years 6005 T5 anodized to 10 microns 6005 T5 anodized to 15 microns Customized 10 years 10 years 6005 T5 anodized to 20 microns 10 years 2 Galvanized Steel Components Galvanized Steel at 85 microns in average Standard Not w...

Page 12: ...rranty period are the responsibility of the customer Where Clenergy attends a site and finds that the Product is not faulty the costs for the visit will be payable by the customer Defective Products shall be uninstalled and or reinstalled at the customer s expense and risk Under certain conditions the Warranty can be extended to more than 10 years at an extra cost available upon request Warranty E...

Page 13: ...t if the Product is stored prior to installing that it is not contaminated by contact with rusty items or other impurities such as dirt and chemicals Should this occur you must clean the Product and make any repairs using approved methods such as galvanized paint and antirust treatments immediately before installation Steel components should be inspected before and after installation and any damag...

Page 14: ... St Clayton VIC 2168 Australia Phone 61 3 9239 8088 Email sales clenergy com au Web www clenergy com au Clenergy Clenergy_global ClenergyClub Clenergy ClenergyGlobal ClenergyClub ClenergyAUS A Clenergy Technologies Company ...

Reviews: