background image

C

JUNCTION
BOX

SCREW

ADJUSTABLE
MOUNTING BARS

JOIST

3

2

2:

 Select the location between two joists to mount the 

    junction box.

3:

 Place the lips of the adjustable mounting bars against the 

    joists. Secure the adjustable bars to the joists with the #8 
    screws.

NOTE:

 

The adjustable mounting bars mount to joists that are 

spaced 14.5"-25" apart.

NOTE:

 

Ensure the opening of the junction box is aligned with 

the center of the desired fixture location. If necessary, adjust the 
junction box location by loosening the screws and sliding the 
junction box to the proper location. Tighten the Phillips screws 
after adjusting.

4:

 Remove a knockout to install a conduit into the junction box.

5:

 Install conduit(s) (if required by local electrical code) and 

    run low-voltage 24VDC power wires coming from the remote 
    power supply to the junction box.

NOTE:

 

Ensure remote power supply wires are present in the 

junction box. Refer to instructions provided with the power 
supply.

D

CONDUIT

JUNCTION
BOX

4

5

E

6:

 Mark a rectangle shape on the drywall where the junction 

    box opening will be located depending on the selected 
    position.

7:

 Cut out the marked rectangle opening, using a "Dremel 

    Multi-Max" with the "wood & drywall" cutting bit.

8:

 Install & finish drywall.

9: 

Complete installation by following steps in Section Three.

RECTANGLE
OPENING

DRYWALL

DREMEL
MULTI-MAX

WOOD & DRYWALL
CUTTING BIT

6

7

10:

 

Optional:

 Use the Goof Plate if the junction box opening 

      has imperfection/ jagged edges. Install the provided 
      goof plate (paint to match prior) with the two screws.

F

SCREW

GOOF PLATE

(ONLY USE IF JAGGED 
PLASTER EDGE,
PAINT TO MATCH)

PLASTER THE EDGE OF
THE JUNCTION BOX

JUNCTION
BOX OPENING
EDGE

10

2

Reviews: