Press STEP 1 key. The STEP 1 button and the DURATION setting LEDs will light up.
The bar graph will show the default DURATION for STEP 1.
1. Press the UP (+) or DOWN (-) arrows to change the DURATION
2. Press the STEP 1 key again to change the SPEED setting. The SPEED setting
LED will light up. The bar graph will show default SPEED for STEP 1.
3. Press UP (+) or DOWN (-) to change the SPEED.
4. Press and STEP or OVERRIDE key to save the DURATION and SPEED settings
for STEP 1. If you decide not to save the settings, pressing the STOP key will
revert back to the previously stored setting.
5. Press STEP 2, STEP 3, or OVERRIDE key. Repeat Steps 1-4 to program the
corresponding DURATION and SPEED for each button.
6. Press START to run the V-Green 165 motor based on the programmed 24 hour
schedule.
7. Pressing the STOP button will stop the V-Green 165 motor.
NOTE: The V-Green 165 motor can only be set to operate on a 24-hour schedule. If a
user attempts to program a schedule with a combined duration for all three steps
greater than 24 hours, the V-Green 165 motor software will retain the current STEP time
duration only and zero out the other two STEP time settings.
V-Green Start-Up
To access the V-Green Start-Up Guide and User Interface Instructions, please visit this
link:
http://images.inyopools.com/cloud/documents/v-green165-usermanual.pdf
PURELINEPOOL.COM
TEL: 407-834-2200
14