PTS 9042x Series Small Cell
AC Power Distribution Load Centers
Installation Guide
20
All Rights Reserved, 2017
www.pactechsol.com/TMOVendor
888-820-3508
4.6 Wiring Service and Load Connections
4.6.1
Wiring to be done in accordance with NEC and Local Jurisdictions Code.
4.6.2
Ensure connections are properly seated in set screw openings prior to tightening per
specifications.
4.6.3
Re-check all connections are labeled
4.6.4
If completed, re-install Dead Front Plate as per Section 5.3
Figure 9: Standard Wiring Practice Example