TSC 1500XL
11
-Proper Grounding and Shielding
Proper grounding and shielding are essential for reliable system operation. Low voltage DC and
communication wiring must be protected from electrical noise introduced by 120v AC wiring,
other voltages and signals which may be present in the building infrastructure.
1.
The main 120v power feeds from the breaker panel to the RB should have a separately
pulled Green ground wire. This should be bonded to the breaker panel source.
Note: Supplied voltage must be constant. If not, constant errors can occur.
Plug all open holes.
1)
After installation of conduit and wire, all open holes must be plugged by electrician.
Wiring Practices:
All AC wiring should be routed away from DC, Communication, and Control wiring and
should never intersect or cross. Failure to do so can cause communication issues with an
installed system.
Ideally locate the Master and Secondary Nodes somewhere easily accessible such as in an
electronics room or catwalk. The reason for this is access to the Manual Control Override
feature and for any service needs.
Do not install the box on the ceiling.
It is not designed to be installed in this manner
and doing so will cause operation problems.
Contact Performance Sports Systems at 800-848-8034 extension 236 for questions or
additional information concerning the TSC 1500-WiFi
installation