OPERATION PREPARATIONS
Unlock load cells
.
Remove the bolt that fix tank platform with chassis, to release tank load cell.
Fill equipment with refrigerant
(New equipment is empty, you need to fill the equipment
with refrigerant and refrigeration oil)
Connect either HP or LP hose with external refrigerant R134a or HFO-1234yf tank, and turn on
the machine, select corresponding refrigerant type, run recovery to fill equipment with refrigerant.
After one refrigerant tank is filled, fill other tank with its corresponding refrigerant.
It is recommended to maintain both tanks at 3-6kg refrigerant.
Air purge
It is recommended to purge the air in equipment tanks every day before turn on the machine. At
left and right sides of machine, air purge manual valves and P-T chart can be found. Turn the
valve to purge the air, strictly abiding by the pressure to be consulted in chart, corresponding to
environmental temperature.