![Project Fire Zonecheck Instruction Booklet Download Page 5](http://html1.mh-extra.com/html/project-fire/zonecheck/zonecheck_instruction-booklet_1614008005.webp)
2
Installation
Zonecheck should be installed by a competent fire sprinkler installer and wired up by a
qualified electrician.
1
Contact building management to inform them of the proposed works.
2
Isolate and drain down selected zone.
3
Orientate the Zonecheck in accordance with the diagrams in this booklet.
4
Install the Zonecheck with two approved grooved couplings (not supplied).
5
Double check that the sprinkler flow arrows on Zonecheck are facing the correct
direction (see diagrams included in this booklet).
6
Fit the key-switch to the wall in a suitable location that is easy to reach from floor level.
7
Wire the Zonecheck pump and flow-switch to the key-switch in accordance with the
diagrams in this booklet.
8
Wire the flow-switch to the appropriate fire-detection panel in accordance with the
diagrams in this booklet.
9
If required, wire monitoring cables from zone valve to key-switch.
10 Wire the appropriate power supply to the key-switch.
11 Proceed to Commissioning instructions.
DO NOT ATTEMPT TO MODIFY ZONECHECK,
TAMPERING WILL VOID THE WARRANTY.
Summary of Contents for Zonecheck
Page 19: ...16 ...