12
COZEBURN INSTALLATION AND OPERATION MANUAL
INSTALLATION
IMPORTANT:
The installation drawings in this manual are typical layouts shown as examples of types of
layout only. We recommend that you engage a professional plumbing and heating company
to ensure that your installation is suitable for your application, will serve your needs and
conform to all local codes.
The Pro-Fab Industries warranty covers the Cozeburn furnace only and does not include
anything outside of the Cozeburn furnace. Pro-Fab Industries takes NO responsibility for
faulty installations, etc. DO NOT modify this unit in any way. Any modification will void the
warranty.
These drawings should help you in establishing a list of material required for a typical
installation. All parts should be available from your Cozeburn provider. Ask your dealer for a
parts list.
Cozeburn
Insulated
supply line
Insulated
return pipe
Filter
Pump
Side arm
heat exchanger
Hot
water
tank
Existing
furnace
Circulating
pump
Mixing
valve
Heat
exchanger
Return
line
Under floor
heating pipes
Figure 1
Typical Installation
Note:
The installation of the Cozeburn as an add-on unit must be installed without changing the function of the controls or
rewiring the original boiler. A wiring interconnection is permitted. The electrical system of both boilers must be powered from a
single branch circuit without exception.