2. Rack/Tower Installation
2-1. Tower Installation
The UPS system is shipped with two sets of feet and 6 extensions (2 short extensions plus 4 long extensions)
that can be used to install the UPS module in the Tower configuration.
A. Install Stand-a-lone. Refer to Figure 1.
Assemble two feet and one short extension as one tower stand as shown in Step 1.
Align the two stands approximately 35 cm apart as shown in Step 2.
Put the UPS module in the stands as shown in Step 3.
B. Install UPS module and one battery bank as shown in Figure 2
below.
Assemble two feet and two long extensions as one tower stand as shown in Step 1.
Align the two stands approximately 35 cm apart as shown in Step 2.
Put the UPS module and battery bank in the stands as shown in Step 3.
Figure 1
Figure 2