COMMISSIONING - Page 19
FIG. 25 MAIN BURNER PRESSURE ADJUSTMENT
Shut down the boiler remove the pressure gauge and refit
the screw in the test nipple ensuring that a tight seal is
made.
Refit the controls cover.
Relight the boiler and heat the system to maximum. Check
for water leaks, turn the boiler off, drain the system whilst
hot.
Refill the system and on sealed systems adjust to the correct
cold fill pressure. Set the pressure gauge pointer to the
system design pressure.
If a by-pass circuit is fitted the by-pass valve should be
adjusted with the boiler operating under minimum load
conditions to maintain sufficient water flow through the boiler
to ensure that the overheat thermostat does not operate
under normal operating conditions.
Pilot Burner
The pilot is pre-set and no adjustment is required. The pilot
flame envelope should cover the electrode tip, see FIG. 29.
If the pilot flame is not as illustrated, remove and clean the
pilot as described in the Servicing Instructions Section 4,
PILOT BURNER, Page 22.
Boiler Thermostat
At its minimum and maximum settings, the thermostat
should control the water flow temperature at approximately
55
0
C—82
0
C (130
0
F—180
0
F).
The thermostat has been calibrated by the makers and no
attempt should be made to re-calibrate it on site. Turn the
thermostat to the ‘0’ position and check that the main burner
shuts down.
Pump Over-Run Thermostat
Will keep the pump running after the boiler has shut down,
as long as the water temperature within the boiler is above
80°C.
The thermostat is preset and no adjustment is possible.
Overheat Thermostat
The overheat thermostat is pre-set and no adjustment is
possible. It will require manually resetting if an overheat
condition occurs. Access to the reset button is through a
hole in the underside of the controls cover, see FIG. 2.
Other Boiler Controls
All boiler mounted controls are designed so that if any fault
should occur they will fail safe. No further setting or checking
is necessary.
External Controls
Check that any other external control connected in the
system, such as clocks and thermostats, control the boiler as
required.
User’s Instructions
A User’s Instructions leaflet is provided with this boiler but
the householder must have the operation of the boiler and
system explained by the Installer. The householder must
also be advised of the importance of annual servicing and of
the precautions necessary to prevent damage to the system
and building, in the event of the system remaining out of
commission in frost conditions.
Summary of Contents for PROFILE LPG 100e
Page 4: ...SITE REQUIREMENTS Page 4 FIG 2 GENERAL ARRANGEMENT ...
Page 10: ...TECHNICAL DATA Page 10 FIG 7 FULLY PUMPED SEALED SYSTEM ...
Page 20: ...COMMISSIONING Page 20 FIG 26 FUNCTIONAL FLOW DIAGRAM HONEYWELL FIG 27 BOILER WIRING DIAGRAM ...
Page 23: ......
Page 25: ......
Page 28: ...Publication No 559472 01 92 SERVICING INSTRUCTIONS Page 26 FIG 30 FAULT FINDING CHART ...