6. Commissioning
Danger! Danger of life by improperly performed work!
Commissioning must only be carried out by an GasSafe heating engineer! The
heating specialist checks the tightnesss of pipelines, the correct functioning of all
regulating, control and safety installations and measures the combustion values.
In case of incorrect operations exists the danger of considerable damage to per-
sons, environment and property!
6.1 Menu-Commissioning
During first commissioning, the menu Commissioning is showing up one-time.
1.
Select
Language
and confirm by pressing OK
2. Select
Year
and confirm
3. Set
Date a
nd confirm
4. Set
Time
and confirm
5. Finalize by pressing OK
Note:
If the menu commissioning is interrupted by pressing ESC, the menu is
showing up again during the next switch-on of the device.
6.2 Switching on
Danger
! Danger of scalding!
Hot water may exit from the blow pipe of the safety
valve.
1.
Switch on boiler electrical isolation
2.
Open gas shut-off device (
1
) and the water shut off valves (
2
and
3
)
3. Open front panel cover and switch on operating switch on the front panel of
the boiler
Commissioning
7308272-03 03.14
Paramount three 30-115 kW
39
Summary of Contents for Paramount 40
Page 1: ...Installation manual Gas condensing boiler Paramount three 30 115 kW ...
Page 23: ...Prior to installation 7308272 03 03 14 Paramount three 30 115 kW 23 ...
Page 25: ...Fig 5 Connection plan Prior to installation 7308272 03 03 14 Paramount three 30 115 kW 25 ...
Page 28: ...4 9 Legend Prior to installation 28 Paramount three 30 115 kW 7308272 03 03 14 ...