VOLTAGE DIVIDER SETTINGS
The secondary voltage divider is set in the factory at a value
of 1:50.
Inside the machine there is a dip-switch (SW1) that can be used
to set 4 other secondary voltage values:
1:20
1:21
1:30
1:40
To access the dip-switch (SW1) proceed as follows (Fig. O):
1) Disconnect the power supply from the system by turning
the line switch on the back panel to the O position. Discon-
nect the machine’s power supply cable from the main pow-
er supply socket in the wall.
2) Remove the plant’s metal lid to access the plant’s second-
ary board.
3) Set the dip-switch (SW1) to one of the configurations avail-
able.
4) Reassemble the machine, following the points above in re-
verse order.
ROBOMAT1 INTERFACE
The SHARK 155 plants, in their special MR version, can eas-
ily be integrated with automatic robotics cutting plants, via the
ROBOMAT 1 interface, which handles all process signals and
regulates the main cutting parameters.
ROBOMAT 1 is a flexible, efficient interface system that satis-
fies all Analogue / Digital connection requirements.
Go to the website http://www.ceaweld.com/portal/cea/down-
load/manuali to download the instruction manual and docu-
mentation available for the equipment being used.
In addition to the ROBOMAT 1 interface, on the back of the
SHARK 155/MR plant there is a 14-pole female connector
(CPC TE Connectivity) for connecting a CNC controller or a
height controller.
The signals available on the machine interface connector, are
indicated in figure N.
USING THE MANUAL PLASMA TORCH ON PLASMA
SHARK, “M / MR” VERSION PLANTS
Manual torches can be used on SHARK “M / MR” version plas-
ma plants for automatic plants as well:
Automatic
cutting torch
Manual torch
Length
SHARK 155/M
SHARK 155/MR
SKM 165
SK 165
6-12 m
FIG. O
ALL OFF SW1 ON SW2 ON SW3 ON SW4 ON
1:20
1:21
1:30
1:40
1:50