8 - COMMISSIONING
8.1 - GENERAL WARNINGS
8.1.1 - SAFETY REQUIREMENTS FOR COMMISSIONING
During commissioning, the risks posed by possible discharges of flammable or noxious gases into the
atmosphere must be assessed.
In the case of installation on distribution networks for natural gas, the risk of explosive mixture (gas/air)
formation inside the pipes should be considered if an inerting procedure of the line is not adopted.
During commissioning operations, unauthorized personnel must stay out.
Commissioning must be carried out by authorized and licensed personnel.
Before commissioning the equipment, it is necessary to check that all shut-off valves (inlet, outlet, bypass if applicable)
are closed.
Commissioning
Operator qualification
• Commissioning technician.
PPE required
The PPE listed in this chart relates to the risk associated with the equipment.
For the PPE required to protect against risks associated with the workplace,
installation or operating conditions, refer to:
• the regulations in force in the country of installation;
•
any indications provided by the Safety Manager at the installation facility.
Tab. 8.50.