16. MAINTENANCE AND OVERHAUL PROGRAMME
The following Maintenance Programme specified on the appropriate PAB
certification for each product is as follows:
In order to carry out this Maintenance Programme in a manner that
achieves the required safety and quality, the following minimum level of
competence is required:
a) For all activities the person leading the task must be able to follow
and carry out the instruction detailed in this document.
b) All safety-critical work must be carried out by persons competent in
accordance with Railway (Safety Critical Work) Regulations 1994.
c) All work relating to the maintenance and overhaul of axle bearings
should be carried out by competent persons.
d) Staff undertaking this work must have been trained and hold
certificates of competency such as: SCW ID; apprentice-Trained
Craftsman/NVQ level 3 in Plant Maintenance; Certificate issued by a
CITB/CTA approved body
– operation for maintenance purposes
only; Re-assessment of competency in accordance with RPA
Standards etc.
e) All staff to have undergone the training course for the appropriate
Permaquip equipment, to the extent of the responsibilities and the
tasks they are asked to be perform by the machine and equipment
owners and their agents.
Always follow local regulations.
All tools and equipment used for testing of speeds, lighting, noise levels,
electrical circuits and all M.O.T. requirements must be calibrated to
National Standards, and only operated by fully trained persons.
Observe Manual Handling Regulations.
Information shown is based upon normal rail mileage and service
conditions. If used in unusual or arduous conditions, then the frequency
of the maintenance must be increased accordingly.
Brake tests must be performed following any repair or replacement of the
brake system or components.
Prior to working on the air braking system drain the air reservoir via the
test point sited to the side of the tank.
Summary of Contents for Kubota RTV X900 RRV
Page 14: ...MAN M O 220_01 24 01 2019 Page 14 of 72...
Page 19: ...MAN M O 220_01 24 01 2019 Page 19 of 72 5 2 Dimensions...
Page 38: ...MAN M O 220_01 24 01 2019 Page 38 of 72 9 5 Hydraulic Rail Gear Schematic...
Page 65: ...MAN M O 220_01 24 01 2019 Page 65 of 72 20 FASTENER TORQUES...
Page 66: ...MAN M O 220_01 24 01 2019 Page 66 of 72...
Page 67: ...MAN M O 220_01 24 01 2019 Page 67 of 72...
Page 68: ...MAN M O 220_01 24 01 2019 Page 68 of 72...
Page 70: ...MAN M O 220_01 24 01 2019 Page 70 of 72...