8.3 Cable length
Table 5. Cables used at the installation
№
Equipment
Cable
length, m,
max
Cable type
Cross-
section,
mm, min
Example
10
Twin cable
1.5
AWG 15; HO5VV-F 2×1.5
1 Power supply
20
Twin cable
2.5
AWG 13; HO5VV-F 2×2.5
2
- Fire Alarm device
- Optional equipment to control
board input and output
30 Twin
cable
0.2
RAMCRO
SS22AF-T 2×0.22
CQR-2
3 RC-panel
40
Eight core cable
0.2
CQR CABS8 8×0.22c
4 ACS-controller
30
Six core cable
0.2
CQR CABS6 6×0.22c
8.4 Installation order
Installation order is described with regards to recommendations, given in Sect. 8.1. Installation
tools are listed in Sect. 8.2. Figure numbers are given in accordance with Fig. 6 and 7.
Speed gate connection layout is given in Fig. 18. Types of cables used are stated in Sect. 8.3. The
example of
ST-01
and
STD-01
connection layout with extra passage lane arrangement is shown in
Fig. 17.
Follow this order to install the speed gate:
1. Install the PS on a designated area in accordance with the instruction given in the operational
documentation.
Attention!
While relocating the section, it is forbidden to hold it by the top cover (10).
Installation and fastening of the speed gate sections should be performed only after
cabling in cable channels and inside of the speed gate being finished
.
Be careful while dismantling the section pieces that has not been fixed on a mounting
surface. Prevent the section from falling down and its pieces from being damaged.
2. Determine the installation location for
Master
and
Slave
sections and for double-sided section
if needed. However, it is necessary to consider the sections relative positioning: the
Master
section panel (side of the double-sided section) should always been placed opposite to the
Slave
section panel (side of the double-sided section).
3. Mark and drill holes for anchor sleeves on the mounting surface for fastening speed gate
sections in accordance with the layouts presented in Fig. 15-16 and in compliance with the
checkpoint design. Use Ø16 mm hard-alloyed drill bit. The drilling depth for standard PFG
IH10 anchor should be 65 mm. Insert the anchor sleeves in the holes so they are flush with the
floor surface.
4. Prepare cable channels in the floor:
Channels for cabling from external devices (PS, RC-panel or ACS-controller, Fire Alarm
device etc.) – to input holes of the
Master
section and input towards double-sided
Master
section;
Channels that link input holes of the opposite sections (double-sided sections) of one
passage lane – for routing DC and CAN cables.
Attention!
Passage lanes that are limited by one-sided sections and / or sides of double-sided sections
are standalone devices which are not connected to each other.
Master
and
Slave
sides of one double-sided section are electrically independent as they
belong to different passage lanes.
5. In the cable channels, route cables from external devices to the sections installation location.
Also, route flexible conduit in the cable channel between the opposite sections (sides of the
sections) for each passage lane. The flexible conduit is used for pulling DC and CAN cables
from the
Slave
section (side of the section) to the
Master
section (side of the section)
.