Commissioning
2
0
1
8
-1
2
27
■
If the alignment LED flashes again, stop turning. Now turn the adjustment
screw half the number of turns in a clockwise direction to get it back to the
middle.
4. To align the horizontal x-adjustment screw, proceed in the same way as
described above.
■
Turn the screw clockwise until the alignment LED flashes slowly.
■
Change the direction of rotation (counterclockwise). Turn and count the
revolutions for as long as the alignment LED remains deactivated.
■
If the alignment LED flashes again, stop turning. Now turn the adjustment
screw half the number of turns in a clockwise direction to get it back to the
middle.
5. Increase the distance between the two devices to the maximum distance.
Readjust the device if necessary.
6. Once you have made the adjustments, tighten the central M6 fixing screw to
fix the position in the horizontal direction.
Parallel light paths
If two light paths are installed next to each other without any optical separation,
the optical data couplers must be installed opposite each other in pairs. This is to
avoid cross-talk. A minimum distance "a" between the beam axes is not required,
provided that the adjacent pairs have the identical overall distance "d."
Figure 5.7
Parallel light paths
F2
F1
F1
F2
a
d