STACK ASSEMBLY SEQUENCE

Step 1. Clamp the fixture in the vise and 

insert the shaft. Pin the shaft with the lock 

spindle inserted in the “ASSEMBLY” hole.

Step 2. Add the first impeller. Tap the collet

into the impeller hub with the collet driver 

until it locks to the shaft and the impeller is 

seated on the fixture.

Step 3. Apply anti-seize oil to the impeller 

threads, add the locknut; hold the impeller 

with the wrench and tighten the locknut 

against the collet. Torque to 52 ft.-lbs.

1

2

3

1st Stage Will Be:

1-Stage Pump: 

 Type F (Step 9) 

All Others: 

Type D 

Add Bearing 

only on 3-Stage

Pumps (type DB

Stage) 

Locknut

Collet

2nd Stage Will Be:

2-Stage Pump: Type F (Step 9)

3-Stage Pump: Type DB

All Others: Type D

Step 4. Remove the lock spindle. Remove 

the shaft from the fixture, seat the bottom 

flange in the fixture, and reinsert the shaft/

impeller assembly into the fixture. Reinsert 

the lock spindle from the opposite side of 

the fixture (that is, in the hole in the fixture). 

For single stage pumps, skip to Step 9.

Step 5. Slide a bowl (see Figure 8) down the 

shaft until it seats on the bottom plate.

Step 6. Slide the next impeller, collet, and 

locknut down the shaft and repeat Steps 2 

and 3. For two-stage pumps, skip now to 

Step 9. For three-stage pumps, add a bearing 

(type DB stage) before going to Step 7.

Step 10. Check for free rotation. If the

stack now rotates freely, it is ready for

installation in the pump.

Step 7. For all pumps with more than three 

stages, use a type D stage. Three-stage 

pumps use type DB (with spacer over the 

locknut) and go to Step 9. NOTE: If your 

pump has reduced diameter impellers (for 

example, a PVM32-6-2), they go in the 

top stages. In a PVM32-6-2, for instance, 

stages 5 and 6 (the top two) are reduced 

diameter. Note that the impeller shroud is 

full diameter; only the vanes are reduced. 

Be sure you do not mix them with full 

diameter impellers.

Step 8. Repeat Steps 5 and 6, following the

order for bowl assembly shown in Figure 8.

Repeat until you have done the next to the

last bowl, then go to Step 9.

Step 9. Add type F stage bowl (with cutouts

for straps). Insert the straps in the holes 

in the bottom plate, hook into the bowl 

cutouts, add nuts and washers, and tighten 

the straps to 4.4 ft.-lbs. (53 in.-lbs.) of 

torque (see Table IV).

Summary of Contents for PVM32

Page 1: ...the system PVM32 SERIES SINGLE AND THREE PHASE VERTICAL MULTISTAGE PUMPS INSTALLATION AND OPERATING INSTRUCTIONS Part A 03 309 2013 Pentair Ltd 10 09 13 Record the following information from the motor...

Page 2: ...tings and report to the carrier any items that are damaged or missing CONFIRM THAT YOU HAVE THE RIGHT PUMP APPLICATIONS AND OPERATING RANGES Pentair multistage in line centrifugal pumps are designed f...

Page 3: ...PVM32 2 2D 27 0 13 9 7 9 2 6 43 5 10 0 PVM32 2 1D 27 0 13 9 7 9 2 6 43 5 10 0 PVM32 2D 27 0 13 9 7 9 2 6 43 5 10 0 PVM32 3 2D 29 8 13 9 7 9 3 1 46 8 10 0 TABLE II Three Phase Maximum Height and Width...

Page 4: ...e inlet pressure can cause the pump to exceed its maximum permissible operating pressure Make sure especially on the inlet side of the pump that there are no airlocks in the system See Figure 4 for co...

Page 5: ...G NOTICE Under no circumstances should the pump be operated without flow through the pump Never operate the pump dry Operation of closed systems or open systems with the liquid level above the pump pr...

Page 6: ...alve has been installed check to be sure that it is completely opened 2 For initial starting the isolation valve in the discharge pipe should be almost closed 3 Start the pump 4 When the piping system...

Page 7: ...98 9 14 125 97 39 32 629 9 945 212 100 14 698 101 34 33 952 10 349 220 104 4 17 188 118 51 39 704 12 102 230 110 0 20 78 143 28 48 002 14 631 240 115 6 24 97 172 17 57 681 17 581 248 120 0 28 79 188 5...

Page 8: ...ets required performance and is operating smoothly and quietly 2 There are no leaks 3 The motor is not overheating 4 Remove and clean all strainers and filters in the system 5 Verify amp draw check mo...

Page 9: ...ix the coupling parts each coupling is a matched pair Step 3 Unscrew the four screws holding the seal carrier and remove the carrier Step 4 Loosen the Allen screws holding the seal about one half turn...

Page 10: ...ise and set the stack on it Lift the shaft enough to allow you to pin it with the locking tool inserted in the DISASSEMBLY hole in the fixture Remove the strap nuts washers and straps Step 2 Remove th...

Page 11: ...a bowl see Figure 8 down the shaft until it seats on the bottom plate Step 6 Slide the next impeller collet and locknut down the shaft and repeat Steps 2 and 3 For two stage pumps skip now to Step 9 F...

Page 12: ...not deform Step 4A Install the Allen screw that secures the bottom bearing in the base Tighten it to 6 ft lbs torque Step 4B If you removed the staybolts at disassembly grease the threads and reinstal...

Page 13: ...shaft seal flange Grease the threads on the Allen screws and install the screws Cross tighten them to 46 ft lbs torque Step 13 Cross tighten the Allen screws holding the seal to 6 ft lbs torque Step 1...

Page 14: ...w B Suction pipe pump partly blocked C Pump is sucking air 6 Pump runs but gives no water A Suction pipe pump blocked B Foot or nonreturn valve is blocked in closed position C Leakage in suction pipe...

Page 15: ...3 5 8 Star Washer 14 5 8 Flat Washer 15 Pump Head 16 Fill Plug 17 O Ring 18 Vent Plug with Needle 19 Shaft 20 Bearing Ring 21 Adapter Ring 22 Washer M10 23 Shaft Capscrew M10X16 Ref No Description 24A...

Page 16: ...is warranty shall be at its option to repair or replace any equipment or its component parts which has a defect covered by this warranty or to refund the purchase price of such equipment or part Under...

Reviews: