1 Phase Simplex
Control Panel for Grinder
and Vortex Pumps
Owner and Operational Manual
293 S. Wright St, Delavan, WI 53115 Phone: 1-866-973-6835 Fax: 800-426-9446
P10063VSM
Introduction
Before proceeding with the installation or operation of the control panel read all instructions thoroughly
as well as comply with all Federal, State and Local Codes, Regulations and Practices. The control
panel must be installed by qualified personnel familiar with all applicable local electrical and mechanical
codes. Refer to the National Electrical Code (NFPA 70). Failure to properly install and test this product
can result in personal injury or equipment malfunction. All conduit connected to the panel must be
sealed with conduit sealant to prevent moisture or gases from entering the panel. NEMA 1 enclosures
are for indoor use only while NEMA 4X panel enclosures may be used indoors or outdoors. Refer to
panel model name-plate on inside of door for enclosure rating. Note: If options are ordered that affect
the number of floats, refer to the panel schematic for complete information.
This Control Panel Is Used With The Following Pumps
G2DT-01
G2DT-21
V1D-01
V1D-21
G2D-01
G2D-21
V15D-01
V15D-21
V2D-21
G3D-01
G3D-21
V2D-01
V3D-01
V3D-21
Safety Guidelines
1.
DO NOT USE WITH FLAMMABLE OR EXPLOSIVE FLUIDS SUCH AS GASOLINE, FUEL OIL, KERO-
SENE, ETC. DO NOT USE IN EXPLOSIVE ATMOSPHERES. CONTROL PANEL SHOULD ONLY BE
USED IN WATER AND WASTEWATER APPLICATIONS THAT ARE NOT RATED AS A HAZARDOUS
LOCATION.
2.
DO NOT WORK ON THE CONTROL PANEL WITH LIVE VOLTAGE APPLIED TO THE CONTROL
PANEL WITH WET HANDS OR WHEN STANDING ON A WET SURFACE.
3.
DISCONNECT ALL ELECTRICAL SERVICE BEFORE WORKING OR HANDLING THE CONTROL
PANEL.
4.
INCOMING VOLTAGE MUST MATCH THE CONTROL PANEL VOLTAGE. REFER TO THE PANEL
SCHEMATIC FOR COMPLETE INFORMATION.
Installation of the Control Panel:
1.
Determine mounting location for the control panel. If splicing is required between the level
switches and the panel, we recommend a junction box. CAUTION! Use conduit sealant and
waterproof wire nuts for connections. Make sure all connections are water tight.
2.
Determine conduit entrance locations on control panel and install per local codes. Check sche-
matic and determine number of power sources required. Use conduit sealant on all conduits to
prevent moisture and gases from entering control panel.
3.
Connect control/alarm and pump power conductors to the proper terminals. The schematic and
terminal blocks will be labeled for proper connection.
4.
Verify correct panel operation after installation of panel, power and level switches are complete.
Page 1 of 10