MACH® Series
Gas-Fired Boiler
Installation
Page 5
3.0 INSTALLATION
WARNING!
Installation and service must be performed by a
qualified installer, service agency, or gas supplier.
3.1
R
ECEIVING AND
S
TORAGE
3.1.1 Initial Inspection
Upon receiving the boiler, inspect it for signs of
shipping damage. Since some damage may be hidden,
unpack the boiler, open the front and side doors and
inspect the internals of the boiler.
Verify that the total number of pieces shown on the
packing slip agrees with those actually received.
Important:
Note any damage, suspected potential
damage, or shortage of materials on the freight bill and
immediately notify the carrier. File all claims for
shortage or damage with the carrier. Claims for
hidden damages must be filed with your carrier within
7 days. The boiler carton is equipped with a “Tip (N)
Tell”. If "Tip (N) Tell” arrow point is blue, or if the
“Tip (N) Tell” is missing, it is likely that the package
has been on its side or tipped over in transit.
3.1.2 Storage Prior to Installation
If the boiler is not installed immediately, it must be
stored in a location adequately protected from the
weather, preferably indoors. If this is not possible,
then it should remain in the shipping container and be
covered by a tarpaulin or other waterproof covering.
Note: controls and other equipment that are
damaged or fail due to weather exposure are not
covered by warranty.
3.2
C
OMPLIANCE WITH
C
ODES
The P-K MACH C1500/C2000
Boiler with standard
components and options complies with American
National Standard/CSA Standard ANSI Z21.13/CSA
4.9, latest edition, Gas-Fired Low Pressure Steam and
Hot Water Boilers.
The heat exchanger is constructed and stamped in
accordance with ASME Boiler and Pressure Vessel
Code, Section IV for 100 psig maximum operating
pressure and/or 200º F maximum temperature.
Installation of the boiler must comply with the
requirements of all national, state and local codes
established by the authorities having jurisdiction.
Authorities having jurisdiction should be consulted
before installations are made.
Within the US, and in the absence of such local
requirements, this boiler should be installed using the
National Fuel Gas Code, ANSI Z223.1/NFPA 54,
latest edition.
In Canada, the equipment shall be installed in
accordance with the current Installation Code for Gas
Burning Appliances and Equipment, CAN/CSA-
B149, latest edition and applicable Provincial
Regulations for the class, which should be carefully
followed in all cases.
Where required by local codes, the installation must
conform to American Society of Mechanical
Engineers Safety Code for Controls and Safety
Devices for Automatically Fired Boilers (ASME
CSD-1).
In the Commonwealth of Massachusetts see the
Supplement for Massachusetts.
3.3
S
ETUP
3.3.1 Foundation and Placement
Provide a firm, level foundation, preferably of
concrete.
WARNING!
The wheels provided with this boiler
are for positioning purposes only. When positioning
this boiler, maintain positive control of it at all times.
Do not attempt to move the boiler on surfaces that are
not level. Failure to heed this warning could result in
personal injury or death.
Lifting the front of the boiler slightly will allow the
boiler to be rolled off the shipping skid onto the
concrete foundation. Once in position, the wheel