background image

 

 

 

 

 

Instructions 

1005101718 

ENVI & MCBA to NURO  

Date: 12/19/2017 

Revision A 

NURO Conversion Instructions 

MACH C1500V-C2000V 

When the main gas shutoff/control valve opens to attempt ignition, the high gas 
pressure switch will trip, causing the NURO touchscreen to display 10011: 

“High 

Gas Limit”

.  Even after re-opening the downstream gas cock inside the boiler, 

10011: 

“High Gas Limit” 

will remain on the NURO display until the boiler is 

manually reset by pressing “Reset Control”. 

14.  Test the ignition system safety shutdown as follows:  

1. Cycle the boiler on by generating a heat request.  (The method for this will 

depend on your boiler configuration.)  

2. During the pre-purge cycle (before ignition), smoothly close the downstream 

manual isolation valve (inside the boiler cabinet) to reduce the gas flow.  

3. Closing the manual isolation valve will prevent a successful ignition, and the 

NURO will display either:  

109: 

“Ignition Failed” 

 

110: 

“Ignition Failure Occurred” 

 

These alarms indicate an ignition failure and the lockout will remain until the 
control is reset.  After completing this test, turn the boiler off, open the 
downstream manual isolation valve, then turn the boiler back on and reset the 
control. 

15.  Test the air switch for proper operation.  Allow the boiler to start.  Remove the tube from 

the air switch, after 30 seconds the control should lock out on air switch not closed.  
reinstall the tube and reset the boilers control. 

16.  Testing the blocked flue switch.  Allow the boiler to start, remove the blocked flue tube 

from the condensate pan and apply a positive pressure to the tube.  Verify that the 
boiler locked out on a blocked flue error.  Reinstall the blocked flue tube and reset the 
control. 

17.  To test the supply, return, flue, and heat exchanger temp sensors you will need to 

disconnect one wire from each sensor.  Verify that the boiler goes into a blocking error 
for each correct sensor. 

18.  To test the high limit, allow the boiler to start, then turn the high limit down slowly and 

verify that the boiler locks out on high limit.  the high limit should be at the same 
temperature as the supply water temperature at the time that it trips.  Turn the high limit 
all the way up, reset the limit and reset the boilers control. 

19.  In order to test the operating limit on the boiler, verify that the boiler turns on below the 

setpoint minus the differential, and shuts down at the setpoint plus the off differential. 

 
 
 
 
 
 
 
 
 
 
 
 
 
 
 

Summary of Contents for HARSCO MACH C1500V

Page 1: ...ch if not avoided could result in death or serious injury NOTICE Each safety device must be maintained and checked per the recommended schedule Refer to Section 6 in the O M Manual for more informatio...

Page 2: ...n be misused which could result in personal injury or death Lockout tagout procedure must be employed when servicing this unit Failure to do so could result in electrocution injury or death Label all...

Page 3: ...al block covers Identify and label all current field wiring on boiler when disconnecting 4 Remove 7 16 nuts as required that hold top panel on as shown in Figure 1 Top panel will need to be lifted at...

Page 4: ...evision A NURO Conversion Instructions MACH C1500V C2000V 5 Using a 1 8 drill bit drill out rivets that fasten high and low voltage terminal blocks 6 Remove 7 16 nuts from 4 inside corners of front fr...

Page 5: ...1005101718 ENVI MCBA to NURO Date 12 19 2017 Revision A NURO Conversion Instructions MACH C1500V C2000V 7 Remove 3 T30 Torx screws from front frame as shown in Figure 3 Remove front frame Remove 7 16...

Page 6: ...12 19 2017 Revision A NURO Conversion Instructions MACH C1500V C2000V 8 With a T30 Torx bit loosen 3 screws that hold control panel in place shown in Figure 3 Figure 3 Loosen T30 Torx screws to contr...

Page 7: ...to wire colors for sensors as new panel will use same colors for sensor wires 9 Control panel can now be slid right lifted off screws and removed from boiler 10 Using a 1 2 wrench remove and replace...

Page 8: ...NURO Date 12 19 2017 Revision A NURO Conversion Instructions MACH C1500V C2000V 11 Install heat exchanger sensor on front section of exchanger Sensor only needs to be finger tight DO NOT OVERTIGHTEN S...

Page 9: ...ront of boiler using supplied T20 self tapping Torx screws 14 Run all internal wires to appropriate safety devices and sensors Types of Wires Colors Identification Return Temperature Sensor Wires Blue...

Page 10: ...R TUBE 16 Install tubing for air switch and blocked flue switch Blocked flue tube will need to be cut to length to ensure that there is not tube slack Tube should be pitched down from switch to conden...

Page 11: ...frame assembly with 4 7 16 nuts in each corner from inside of cabinet 18 Install 3 T30 Torx screws along bottom of front frame assembly 19 Install front door on hinge pins 20 Install NURO touch screen...

Page 12: ...ions MACH C1500V C2000V 21 Insert green electric plug D1 and D2 into NURO control and attach all ground wires to front door ground lug 22 Install field wiring to new terminal boxes per wiring terminal...

Page 13: ...vision A NURO Conversion Instructions MACH C1500V C2000V 24 Flame Rectification Signal Lead wire shown in Figure 12 will not be used Use cap supplied in kit to cover end of wire connection Figure 13 G...

Page 14: ...Instructions 1005101718 ENVI MCBA to NURO Date 12 19 2017 Revision A NURO Conversion Instructions MACH C1500V C2000V Figure 14 Figure 15 Heat Exchanger Sensor and Wires Blower Plugs...

Page 15: ...Instructions 1005101718 ENVI MCBA to NURO Date 12 19 2017 Revision A NURO Conversion Instructions MACH C1500V C2000V Figure 16 High Limit Probe Low Water Cut Off Figure 17...

Page 16: ...rols to boiler 570 421 7500 and press 2 for technical support 26 After pairing is complete with technical support re energize gas supply to unit 27 Perform Runout Procedure 28 Perform factory start up...

Page 17: ...urn off the boiler s circulating pump Isolate the boiler from the system Drain the water level below the low water cut off probe Turn the boiler back on It should not operate and a manual lockout rese...

Page 18: ...ownstream manual isolation valve then turn the boiler back on and reset the control 15 Test the air switch for proper operation Allow the boiler to start Remove the tube from the air switch after 30 s...

Page 19: ...Instructions 1005101718 ENVI MCBA to NURO Date 12 19 2017 Revision A NURO Conversion Instructions MACH C1500V C2000V...

Page 20: ...Instructions 1005101718 ENVI MCBA to NURO Date 12 19 2017 Revision A NURO Conversion Instructions MACH C1500V C2000V...

Page 21: ...Instructions 1005101718 ENVI MCBA to NURO Date 12 19 2017 Revision A NURO Conversion Instructions MACH C1500V C2000V...

Reviews: