Instructions
1005101718
ENVI & MCBA to NURO
Date: 12/19/2017
Revision A
NURO Conversion Instructions
MACH C1500V-C2000V
25. Re-energize power to unit. DO NOT ENERGIZE GAS. Call tech support for help pairing
controls to boiler (570-421-7500 and press 2 for technical support).
26. After pairing is complete with technical support, re-energize gas supply to unit.
27. Perform Runout Procedure.
28. Perform factory start up and fill out start up report located in O&M manual and check all
safety devices per O&M manual to ensure all are working properly.
29. Re-Install side and top panels of boiler.
Figure 18
Ignitor Ground Wires