Parkray Inset Chevin 20B Installation And Operating Instructions Manual Download Page 12

JINCHW09 Rev A 12/05/14 

Commissioning and Handover 

Upon  completion  of  the  installation,  allow  a 
suitable  period  of  time  for  any  fire  cement  and 
mortar to dry out.  A small fire may then be lit and 
checked to ensure the smoke and fumes are taken 
from the stove up the chimney and emitted safely 
to atmosphere.  Do not run the stove at full output 
for at least 24 hours. 
 
On 

completion 

of 

the 

installation 

and 

commissioning,  ensure  that  the  operating 
instructions  and  operating  tools  for  the  stove  are 
left  with  the  customer.    Advise  the  customer  on 
the  correct  use  of  the  appliance  with  the  fuels 
likely  to  be  used  on  the  stove  and  warn  them  to 
use only the recommended fuels for the stove. 
 
Advise  the  user  on  what  to  do  should  smoke  or 
fumes be emitted from the stove.   
 
The user should be warned to use a fireguard to BS 
6539  in  the  presence  of  children,  aged  and/or 
infirm persons. 
 

Operating Instructions 

Read the ‘General Guidance’ Section at the start 
of these instructions before operating your stove 
for the first time. 
 
Allow sufficient clearance between the stove and 
pictures, plasma screen televisions or ornaments 
etc,  as  these  could  be  damaged  and  could 
potentially  create  a  fire  hazard  (For  more 
information read the ‘Material Clearance’ section 
of these installation instructions). 
 
WARNING  –  This  appliance  will  be  hot  when  in 
operation  and  due  care  should  be  taken.  The 
supplied operating tool or gloves may be used to 
open the door and operate the air controls. 
 

A

EROSOLS

 

Do not use an aerosol spray on or near the stove 
when it is alight. 
 

A

IR 

C

ONTROLS

 

Installed and used correctly this stove will burn 
cleanly and efficiently. Therefore, to avoid the 
disappointment of poor performance, please 
familiarize yourself with the controls and their 
recommended settings before use.

 

T

HERMOSTAT

 

The thermostat is controlled by the knob on the 
side of the stove with settings from 0 - 10. The 
thermostat generally operates between 50° to 90°. 
Experiment with the settings to find the desired 
temperature. 
 

 

S

ECONDARY 

A

IR

 

Secondary air is controlled via the slider above the 
door(s), it is this “Airwash” that keeps a clean and 
uninterrupted view of the fire. 
  

 

 

L

OCOMOTIVE 

G

RATE

 

Your Parkray Ltd Stove is fitted with a locomotive 
type grate. So that de-ashing can be carried out 
cleanly and easily, it is riddled from the outside of 
the stove with the doors closed. 
 

 

 

SHUT 

OPEN 

Summary of Contents for Inset Chevin 20B

Page 1: ...JINCHW09 Rev A 12 05 14 Inset Chevin 20B Installation and Operating Instructions ...

Page 2: ...sion at 13 O2 0 33 Mean Flue Gas Temperature 385 C EFFICIENCY 69 9 Flue Gas Mass Flow 14 1g s Maximum operating water temperature in C 100 C Maximum operating pressure in bar 1 2Bar Minimum clearance to combustible material Top of Fire Surround 150mm Side of Fire Surround 75mm Side Wall 200mm This appliance is suitable for intermittent burning This appliance is not suitable for use in a shared flu...

Page 3: ...ither installing the appliance correctly or ensuring regular servicing and maintenance of the appliance and chimney system HEALTH AND SAFETY PRECAUTIONS Special care must be taken when installing the stove such that the requirements of the Health and Safety at Work Act are met HANDLING Adequate facilities must be available for loading unloading and site handling FIRE CEMENT Some types of fire ceme...

Page 4: ...stances the stove should not be used A professional flue installer will be able to advise on solutions to this problem e g anti downdraught cowl CO ALARM Your installer should have fitted a CO alarm in the same room as the appliance If the alarm sounds unexpectedly follow the instructions given under Warning Note above DO NOT FIT AN EXTRACTOR FAN IN THE SAME ROOM AS THIS APPLIANCE IN THE EVENT OF ...

Page 5: ...c fires and therefore not suitable for solid fuel HEARTH REQUIREMENTS A constructional hearth with a minimum thickness of 120mm should be provided This constructional hearth should extend to at least 244mm in front of the stove and 121mm at the sides The constructional hearth should be made of solid non combustible material and can include any solid non combustible floor The boundary of the hearth...

Page 6: ... installations see below there should be no combustible material within 200mm of either side of the stove or 275mm above No combustible furniture should be placed any closer than 700mm from the front of the stove FIRE SURROUNDS Please check the suitability of any fireplace surround for closed solid fuel appliances before installation Parkray Ltd cannot be held responsible for any fault arising thr...

Page 7: ...itting the stove This will make handling the stove easier allow access to fixings and the flue outlet as well as protect the internal components from damage during the installation process 1 Open the door s and remove the ashpan 2 Remove the fuel retainer by lifting off of its supports and remove from firebox 3 Remove the catch bar front plate by lifting until the widest section of the keyhole slo...

Page 8: ...e fire box 5 Remove the grate bars by lifting the front up off the cam bar and sliding forward off the rear grate support and lifting out of the firebox Repeat with remaining grate bars 6 Remove the baffle by sliding it forward until it reaches its stop Then lift and slide forward until clear of its supports and lower into the firebox ...

Page 9: ...ed due to under or over specification of the appliance in any installation Do Not Under any circumstances connect the stove to a sealed pressurised heating system or unvented hot water cylinder Do Not Link the stove into a heating or hot water system with an existing boiler without the use of suitable equipment such as a neutralizer When fitting this type of system the neutralizer manufacturer s i...

Page 10: ...circulating pump from operating until the gravity circuit is up to temperature FLUE CONNECTION N B An adjustable flue bend may be required for some installations If connecting to a stainless liner a proprietary single wall flue adaptor will be required It is recommended that a short length of flue pipe is connected before the liner If connecting to an existing masonry chimney it is recommended tha...

Page 11: ...igh Limit Thermostat 90 C Circulating Pump Low Limit Thermostat 45 C Time Switch Drain Cock Wiring Diagram for general guidance only All electrical work must be carried out by a competent electrician in accordance with the rules in force and the instructions provided by the circulating pump and heating controls manufacturer Two Tapping System Four Tapping System ...

Page 12: ...es plasma screen televisions or ornaments etc as these could be damaged and could potentially create a fire hazard For more information read the Material Clearance section of these installation instructions WARNING This appliance will be hot when in operation and due care should be taken The supplied operating tool or gloves may be used to open the door and operate the air controls AEROSOLS Do not...

Page 13: ...he grate allowing the flames to become established before placing several pieces of small dry kindling in a criss cross fashion above the firelighters taking care not to smother the fire Close the stove door Once the kindling is well alight open the door and build the fire by gradually adding fuel closing the door afterwards Once the fire is established gradually close the secondary air control un...

Page 14: ...h the appliance to reduce condensation and subsequent damage leave the air controls fully open If the appliance has been unused for a long period such as during the spring and summer months a competent person should check the chimney for potential obstructions before lighting the stove i e get the chimney swept before the start of the heating season AS NECESSARY Baffle This should be removed and c...

Page 15: ...alled Manniglas The glass gasket will have to be replaced when a new piece of glass is fitted as the gaskets become brittle after firing the stove Over time you may find that the gasket changes colour This is due to a reduction in the pigment used in the manufacture of the product and no cause for concern De ashing De ashing should be carried out on a regular basis to avoid a build up of ash and e...

Page 16: ...ormation SINGLE DOOR SPARES SINGLE DOOR HCE09 008 DOOR HANDLE AVA08 029MB DOOR GLASS HCE09 102 ROPE SEALING KIT SCPCB900SDRSK DOOR CATCH ASSEMBLY TDI05 ARRT 011MB GLASS CLIP HHR08 046 GLASS CLIP SCREW FSJM05008SS GLASS GASKET HCE09 101 ...

Page 17: ...NDLE AVA08 020MB DOOR GLASS HCE09 031 GLASS GASKET HCE09 030 DOOR CATCH ASSEMBLY AVI05 ARRT 0012MB ROPE SEALING KIT SCPCB900DDRSK GLASS CLIP SCREW FSJM05008SS GLASS CLIP HHR08 046 LEFT HAND DOOR TDI05 008 GLASS CLIP HHR08 046 GLASS CLIP SCREW FSJM05008SS ROPE SEALING KIT SCPCB900DDRSK GLASS GASKET HCE09 030 ...

Page 18: ...ARRT 021 GRATE BARS UPPER 112 032 LOWER 112 033 OPERATING TOOL HFR07 040 ASHPAN HCW09 ARRT 010 CATCH BAR SINGLE DOOR HCW09 ARRT 017 DOUBLE DOOR HCW09 ARRT 018 FUEL RETAINER HCW09 ARRT 025 HINGE PIN FRRE08 1 75 HINGE HH06 050 BRICK LEFT HCW09 051A RIGHT HCW09 051B BAFFLE SUPPORT HCW09 ARRT 013 CAM BAR HCW09 ARRT 020 ...

Reviews: