SWING FRAMES
DATE: 08/29/2014
INSTALLATION GUIDELINES
Page 15 of 20
STEP 9
Install appropriate age level sticker on swing frame. Full bucket seats require a 2-5 label - all other
seats require a 5-12 label. For safety reasons, do not attach swing chains or seats to swing frame until
playground is ready to open.
NOTE:
Swing seats and chains sold separately.
STEP 7
Using adequate manpower, turn swing frame upright and set into place in footings. Block and brace to
correct height and make sure swing frame is level and plumb.
NOTE:
Center of top rail needs to be 96”
above finished surfacing.
Detail C
STEP 5
Select top rail(s) of swing frame and vertical posts. Insert top rails fully into 5”x5” receivers with swing
hanger tabs at 6:00. Install and tighten set screws (see Detail C).
Top Rail
Top Rail
1/2”x3/4”
Set Screw
1/4”x1” Drive Pin
(top of one receiver,
bottom of other)
1/4”x1”
Drive Pin
(top of one receiver,
bottom of other)
1/4”x1” Drive Pin
Top Rail
STEP 6
Select 1/4”x1” drive pins (one per saddle and two per receiver). Drill one 1/4” hole in each post through
back of each saddle and two 1/4” diagonal holes through opposite sides of each receiver in the flat area
by attachment hardware (see Detail B and Detail C).
NOTE:
Drill hole at top on one side of receiver and
at bottom on other side. Place drive pins in holes and tap into place.
STEP 8
Pour concrete into footings to correct level.
NOTE:
Concrete must have a minimum rating of 2,500 psi
and must be mixed per manufacturer’s recommendations. Fill remainder of hole with dirt.
Allow concrete
to harden for at least 48 hours before use.