2.1.1. Leakage Current Cold Check
1. Unplug the AC cord and connect a jumper between the two
prongs on the plug.
2. Measure the resistance value, with an ohmmeter, between
the jumpered AC plug and each exposed metallic cabinet
part on the equipment such as screwheads, connectors,
control shafts, etc. When the exposed metallic part has a
return path to the chassis, the reading should be between
1Mohm and 5.2Mohm.
When the exposed metal does not have a return path to
the chassis, the reading must be
.
Figure 1
2.1.2. Leakage Current Hot Check (See
Figure 1.)
1. Plug the AC cord directly into the AC outlet. Do not use an
isolation transformer for this check.
2. Connect a 1.5kohm, 10 watts resistor, in parallel with a
0.15µF capacitors, between each exposed metallic part on
the set and a good earth ground such as a water pipe, as
shown in Figure 1.
3. Use an AC voltmeter, with 1000 ohms/volt or more
sensitivity, to measure the potential across the resistor.
4. Check each exposed metallic part, and measure the
voltage at each point.
5. Reverse the AC plug in the AC outlet and repeat each of the
above measurements.
6. The potential at any point should not exceed 0.75 volts
RMS. A leakage current tester (Simpson Model 229 or
equivalent) may be used to make the hot checks, leakage
current must not exceed 1/2 milliamp. In case a
measurement is outside of the limits specified, there is a
possibility of a shock hazard, and the equipment should be
repaired and rechecked before it is returned to the
customer.
2 Safety Precautions
2.1. General Guidelines
1. When conducting repairs and servicing, do not attempt to modify the equipment, its parts or its materials.
2. When wiring units (with cables, flexible cables or lead wires) are supplied as repair parts and only one wire or some of the wires
have been broken or disconnected, do not attempt to repair or re-wire the units. Replace the entire wiring unit instead.
3. When conducting repairs and servicing, do not twist the Faston connectors but plug them straight in or unplug them straight out.
4. When servicing, observe the original lead dress. If a short circuit is found, replace all parts which have been overheated or
damaged by the short circuit.
5. After servicing, see to it that all the protective devices such as insulation barriers, insulation papers shields are properly
installed.
6. After servicing, make the following leakage current checks to prevent the customer from being exposed to shock hazards.
5
TH-42PZ77U
Summary of Contents for Viera TH-42PZ77U
Page 4: ...1 Applicable signals 4 TH 42PZ77U ...
Page 19: ...8 Location of Lead Wiring 8 1 Lead of Wiring 1 19 TH 42PZ77U ...
Page 20: ...8 2 Lead of Wiring 2 20 TH 42PZ77U ...
Page 21: ...8 3 Lead of Wiring 3 21 TH 42PZ77U ...
Page 22: ...8 4 Lead of Wiring 4 22 TH 42PZ77U ...
Page 23: ...8 5 Lead of Wiring 5 23 TH 42PZ77U ...
Page 24: ...8 6 Lead of Wiring 6 24 TH 42PZ77U ...
Page 28: ...9 4 No Picture 28 TH 42PZ77U ...
Page 35: ...11 4 Adjustment Volume Location 11 5 Test Point Location 35 TH 42PZ77U ...
Page 37: ...37 TH 42PZ77U ...
Page 65: ...15 1 Schematic Diagram Note 15 Schematic and Block Diagram TH 42PZ77U 65 ...
Page 134: ...TH 42PZ77U 134 ...
Page 135: ...16 Exploded Views Replacement Parts List 16 1 Exploded Views 135 TH 42PZ77U ...
Page 136: ...16 2 Packing Exploded Views Accessories 136 TH 42PZ77U ...
Page 137: ...16 3 Packing Explode Views Stand 137 TH 42PZ77U ...
Page 138: ...16 4 Replacement Parts List Notes 138 TH 42PZ77U ...