Connect a Terminal or Emulator to the SER MGT Port
“Connect a Terminal or Emulator to the SER MGT Port” on page 67
.
Related Information
■
“Rear Panel Components (Installation)” on page 13
■
“Powering On the Server for the First Time” on page 65
Connect a Terminal or Emulator to the SER MGT Port
Prior to powering on the server for the first time, make a serial connection to the SP. After
making this serial connection, you will be able to view the system messages when you connect
the power cords.
1.
Confirm that you have completed the following tasks.
a.
Completed the preparation for installation.
“Preparing for Installation” on page 21
b.
Completed the installation of the server in a rack.
“Installing the Server” on page 25
c.
Connected the necessary cables.
“Connecting Cables” on page 51
2.
Connect a terminal or a terminal emulator (PC or workstation) to the server SER
MGT port.
3.
Configure a terminal or terminal emulator with these settings:
■
9600 baud
■
8 bits
■
No parity
■
1 Stop bit
■
No handshake
A null modem configuration is needed, meaning the transmit and receive signals are reversed
(crossed over) for DTE to DTE communications. You can use the supplied RJ-45 crossover
adapters with a standard RJ-45 cable to achieve the null modem configuration.
Powering On the Server for the First Time
67
Summary of Contents for SPARC T7-1
Page 1: ...SPARC T7 1 Server Installation Guide Part No E54979 01 October 2015 ...
Page 2: ......
Page 8: ...8 SPARC T7 1 Server Installation Guide October 2015 ...
Page 20: ...20 SPARC T7 1 Server Installation Guide October 2015 ...
Page 50: ...50 SPARC T7 1 Server Installation Guide October 2015 ...
Page 64: ...64 SPARC T7 1 Server Installation Guide October 2015 ...
Page 84: ...84 SPARC T7 1 Server Installation Guide October 2015 ...